ERCOT·WATCH Search ercot.com  ⌕
NOGRR #145 · Revision Request

NOGRR145  Alignment with NPRR705, Provides Consistency for References to the End Date of the Generation Interconnection Process

Approved sponsor ERCOT posted 2015-05-20 ercot.com
ReasonAdministrative
Created2015-06-18
Sections Affected
2.2.6
Summary
In the Resource Interconnection Handbook, the term “commercial operations” has a different meaning to Resource Entities and financial institutions involved in construction and financing of Generation Resources than it does in the context of performance testing by ERCOT for new Generation Resources. This Nodal Operating Guide Revision Request (NOGRR) aligns the Nodal Operating Guides with NPRR705 by replacing various terms used to refer to the date on which Generation Resources complete the Resource interconnection process with the proposed defined terms “Commercial Operations Date” and “Resource Commissioning Date” to provide consistency for references to the end of the generation interconnection process.
Action Log 7 milestones
Documents 11
NameTypePostedClassification
145NOGRR-01 Alignment with NPRR705, Provides Consistency for References to the End Date of the Generation Interconnection Process 052015 doc May 20 '15 Revision Request
145NOGRR-02 Impact Analysis 052015 doc May 20 '15 Staff Report
145NOGRR-03 OWG Report 061815 doc Jun 19 '15 Committee Report
145NOGRR-04 OWG Report 072315 doc Jul 27 '15 Committee Report
145NOGRR-05 OWG Report 082015 doc Aug 21 '15 Committee Report
145NOGRR-06 OWG Report 091715 doc Sep 21 '15 Committee Report
145NOGRR-07 ROS Report 100815 doc Oct 12 '15 Committee Report
145NOGRR-08 TAC Report 102915 doc Oct 30 '15 Committee Report
145NOGRR-09 Revised Impact Analysis 111115 doc Nov 11 '15 Staff Report
145NOGRR-10 TAC Email Vote 121615 xls Dec 17 '15 Revision Request Ballot
145NOGRR-11 TAC Report 121615 doc Dec 17 '15 Committee Report
Meetings That Took It Up 8
DateMeetingCommitteeStatus
Nov 19 '15 TAC Meeting TAC Concluded
Nov 17 '15 OWG Meeting OWG Concluded
Oct 29 '15 TAC Meeting TAC Concluded
Oct 22 '15 OWG Meeting OWG Concluded
Oct 8 '15 ROS Meeting ROS Concluded
Sep 17 '15 OWG Meeting OWG Concluded
Aug 20 '15 OWG Meeting OWG Concluded
Jul 23 '15 OWG Meeting OWG Concluded