NOGRR #135 · Revision Request
NOGRR135 Constraint Management During Energy Emergency Alert
- ROS Mar 12 '15
- TAC Apr 23 '15
- BOARD —
- PUCT —
ReasonAddresses current operational issues
Created2014-08-19
Sections Affected
4.2.34.5.24.5.34.5.3.1
Summary
This Nodal Operating Guide Revision Request (NOGRR) seeks to improve management of congestion during an Energy Emergency Alert (EEA) by proposing: 1. Language that provides a mechanism for ERCOT Operations to manage constraints in EEA 2 or 3 to higher Facility ratings when applicable for those constraints identified as limiting generation output; and 2. Language that reconsiders use of double-circuit contingencies during emergency operations based on Grid conditions
Timeline
- Jul 23
-
Aug 19
OWG OWG MeetingOWGDeferred/Tabled“Consensus to table NOGRR135 for one month.” — Passed→ OWG for consideration
- Sep 24
-
Oct 6
Listed without action at 1 meeting
- Oct 22
- Oct 30
-
Nov 19
OWG OWG MeetingOWGRecommended for Approval Amended by the Nov 18 '14 CenterPoint Energy comments“To recommend approval of NOGRR135 as amended by the 11/18/14 CenterPoint Energy comments.” — Passed→ OWG for IA review.
-
Jan 26
OWG OWG MeetingOWGDeferred/Tabled“To table NOGRR135 for one month.” — Passed→ Impact Analysis Consideration
-
Feb 19
OWG OWG MeetingOWGRecommended for Approval Forwarded → ROS Amended by the Jan 21 '15 ERCOT comments“To endorse and forward to ROS the 1/26/15 OWG Report as amended by the 1/21/15 ERCOT comments and the Impact Analysis for NOGRR135.” — Passed→ Revision Request Consideration
-
Mar 12
ROS ROS MeetingROSRecommended for Approval“To recommend approval of NOGRR135 as recommended by OWG in the 2/19/15 OWG Report.” — Passed→ Revision Request Consideration
- Mar 26
-
Apr 23
TACEmail Vote / Unlisted MeetingTACApproved“Voted via e-mail vote to approve NOGRR135 as recommended by ROS in the 3/12/15 ROS Report.” — Passed
-
—
Posted since the last meeting