NOGRR #132 · Revision Request

NOGRR132  Automatic Under-Voltage and Under-Frequency Load Shedding Protection Systems --Load Restoration

Approved sponsor ERCOT posted 2014-05-13 ercot.com
ReasonParagraph (4) of Section 11.4, Mitigation Plan, states, "Restoration of any Load shed by executing the Mitigation Plan shall be coordinated with ERCOT." To improve reliability of the ERCOT System, ERCOT proposes similar language in Section 6.2.6.3.6 to provide a reasonable level of assurance that Load restoration will not exceed capability limits of Generation Resources or Transmission Facilities. Additionally, ERCOT proposes to use similar language in Paragraph (5) of Section 2.6.1 for consistency and clarity that coordination is expected for any of the Load shed restoration with UFLS, UVLS, or Constraint Management Plans with Load shed.
Created2014-06-25
Sections Affected
2.6.16.2.6.3.6
Summary
Adds a requirement for Under-Frequency Load Shedding (UFLS) and Under-Voltage Load Shedding (UVLS) systems Load restoration coordination consistent with that of manually shed Load for EEA 3 or a Constraint Management Plan.
Action Log 8 milestones
Amendments
DateBodyMotionResult
Jan 26 '15OWG To endorse and forward NOGRR132 as amended by the 1/22/15 CNP comments and revised by OWG and the associated Impact Analysis.Passed
Documents 11
NameTypePostedClassification
132NOGRR-01 Automatic UVLS and UFLS Protection Systems - Load Re doc May 13 '14 Revision Request
132NOGRR-02 Impact Analysis 051314 doc May 13 '14 Staff Report
132NOGRR-03 OWG Report 062514 doc Jun 27 '14 Committee Report
132NOGRR-04 OWG Report 072214 doc Jul 24 '14 Committee Report
132NOGRR-05 OWG Report 081914 doc Aug 21 '14 Committee Report
132NOGRR-06 ROS Report 100614 doc Oct 8 '14 Committee Report
132NOGRR-07 ROS Report 010815 doc Jan 12 '15 Committee Report
132NOGRR-08 CNP Comments 012215 doc Jan 22 '15 Revision Request Comments
132NOGRR-09 OWG Report 012615 doc Jan 29 '15 Committee Report
132NOGRR-10 ROS Report 020515 doc Feb 9 '15 Committee Report
132NOGRR-11 TAC Report 022615 doc Mar 2 '15 Committee Report
Meetings That Took It Up 11
DateMeetingCommitteeStatus
Feb 26 '15 TAC Meeting TAC Concluded
Feb 5 '15 ROS Meeting ROS Concluded
Jan 26 '15 OWG Meeting OWG Concluded
Jan 8 '15 ROS Meeting ROS Concluded
Oct 30 '14 ROS Meeting ROS Concluded
Oct 6 '14 Joint ROS/WMS Meeting ROS Concluded
Sep 24 '14 OWG Meeting OWG Concluded
Sep 4 '14 ROS Meeting ROS Concluded
Aug 19 '14 OWG Meeting OWG Concluded
Jul 22 '14 OWG Meeting OWG Concluded
Jun 25 '14 OWG Meeting OWG Concluded