Meeting · PLWG
PLWG Meeting
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 Room 206A
VirtualWebEx / Teams
Dial-in877-668-4493
Revision Requests On The Agenda
Agenda 10 items
- 1. Antitrust Admonition — B. Bell · 9:30 a.m.
- 2. Update on ROS, TAC and Board Activity on PLWG Matters Board Activity: None ROS Activity: ROS Approved PGRR036 ROS Approved PGRR038 with Option 1 (95% in language) ROS directed PLWG to develop a Generation Deliverability Criteria — B. Bell
- 3. PGRR035: DC Tie Interconnection Process PGRR035 defines process for ERCOT to administer requests from Stakeholders for interconnection to ERCOT grid for DC Ties Issue continues to be tabled to allow assessment of broad set of issues raised by ERCOT legal involving planning/market/operations — B. Bell
- 4. Planning Guide 6.9: Air/Water Permit Attestation Discussion — J. Billo
- 5. Review Load Scaling Methodologies Used in Planning Studies — J. Billo/S. Borkar
- 6. CDR and Planning Study Model Differences — B. Bell
- 7. Generation Deliverability Criteria Develop Criteria and Planning Guide Language — B. Bell/J. Billo
- 8. Additional Items
- 9. Next Meeting: August 20, 2014
- Adjourn · 3:30 p.m.