PGRR #38 · Revision Request

PGRR038  Require ERCOT to Report Circuits Loaded Above 95% of Their Facility Rating

Approved sponsor ERCOT posted 2014-05-21 ercot.com
ReasonAddresses current operational issues; and Other: The Operations and Planning Synchronization Task Force (OPSTF) identified several factors that could lead to overloads in operations that were not observed in planning studies. This PGRR will require ERCOT to report circuits that are near overload so that planners are aware of them.
Created2014-07-10
Approved2014-08-12
Sections Affected
3.1.1.2
Summary
This Planning Guide Revision Request (PGRR) requires ERCOT to report when circuits are loaded above 95% of their Facility Rating for single contingency events in the annual Regional Transmission Plan.
Action Log 3 milestones
Amendments
DateBodyMotionResult
Jul 10 '14ROS To recommend approval of PGRR038 as revised by ROS with Option 1.Passed
Documents 7
NameTypePostedClassification
038PGRR-01 Require ERCOT to Report Circuits Loaded Above 95% of doc May 21 '14 Revision Request
038PGRR-02 Impact Analysis 052114 doc May 21 '14 Staff Report
038PGRR-03 PLWG Report 061814 doc Jun 23 '14 Committee Report
038PGRR-04 ERCOT Comments 070314 doc Jul 3 '14 Revision Request Comments
038PGRR-05 ROS Report 071014 doc Jul 18 '14 Committee Report
038PGRR-06 TAC Report 073114 doc Aug 1 '14 Committee Report
038PGRR-07 Board Report 081214 doc Aug 14 '14 Committee Report
Meetings That Took It Up 6
DateMeetingCommitteeStatus
Aug 20 '14 PLWG Meeting PLWG Concluded
Aug 12 '14 Board of Directors Meeting BOARD Concluded
Jul 31 '14 TAC Meeting TAC Concluded
Jul 23 '14 PLWG Meeting PLWG Concluded
Jul 10 '14 ROS Meeting ROS Concluded
Jun 18 '14 PLWG Meeting PLWG Concluded