PGRR #138 · Revision Request
PGRR138 Large Load Interconnection Study Review and Approval Process
ReasonStrategic Plan Objective 2
Created2026-01-08
Sections Affected
9.4
Summary
This Planning Guide Revision Request (PGRR) modifies Section 9.4 to improve the transparency and efficiency of requirements related to the LLIS report and follow-up.
Action Log 1 milestones
-
Jan 8
ROSDeferred/Tabled→ ROS for consideration
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Jan 8 '26 | ROS | Motion Carries | 7.5 | 0 | 0 | xls |
Documents 4
| Name | Type | Posted | Classification |
|---|---|---|---|
| 138PGRR-01 Large Load Interconnection Study Review and Approval Process 120125 | docx | Dec 1 '25 | Revision Request |
| 138PGRR-02 ROS Ballot 010826 | xls | Jan 12 '26 | Revision Request Ballot |
| 138PGRR-03 ROS Report 010826 | docx | Jan 12 '26 | Committee Report |
| 138PGRR-04 Request for Withdrawal 052226 | doc | May 22 '26 | Revision Request |
Meetings That Took It Up 6
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 4 '26 | ROS Meeting | ROS | Concluded |
| May 7 '26 | ROS Meeting | ROS | Concluded |
| Apr 2 '26 | ROS Meeting | ROS | Concluded |
| Mar 5 '26 | ROS Meeting | ROS | Concluded |
| Feb 5 '26 | ROS Meeting | ROS | Concluded |
| Jan 8 '26 | ROS Meeting | ROS | Concluded |