PGRR #136 · Revision Request
PGRR136 Large Load Interconnection Study Scope Documentation
ReasonStrategic Plan Objective 2
Created2026-01-08
Sections Affected
9.3.2
Summary
This Planning Guide Revision Request (PGRR) implements targeted revisions to Section 9.3.2 to strengthen Large Load Interconnection Study (LLIS) scoping requirements and improve transparency across ERCOT, Transmission Service Providers (TSPs), and Interconnecting Large Load Entities (ILLEs) by enhancing documentation.
Action Log 1 milestones
-
Jan 8
ROSDeferred/Tabled→ ROS for consideration
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Jan 8 '26 | ROS | Motion Carries | 7.5 | 0 | 0 | xls |
Documents 4
| Name | Type | Posted | Classification |
|---|---|---|---|
| 136PGRR-01 Large Load Interconnection Study Scope Documentation 112525 | docx | Nov 25 '25 | Revision Request |
| 136PGRR-02 ROS Ballot 010826 | xls | Jan 12 '26 | Revision Request Ballot |
| 136PGRR-03 ROS Report 010826 | docx | Jan 12 '26 | Committee Report |
| 136PGRR-04 Request for Withdrawal 052226 | doc | May 22 '26 | Revision Request Comments |
Meetings That Took It Up 6
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 4 '26 | ROS Meeting | ROS | Concluded |
| May 7 '26 | ROS Meeting | ROS | Concluded |
| Apr 2 '26 | ROS Meeting | ROS | Concluded |
| Mar 5 '26 | ROS Meeting | ROS | Concluded |
| Feb 5 '26 | ROS Meeting | ROS | Concluded |
| Jan 8 '26 | ROS Meeting | ROS | Concluded |