PGRR #106 · Revision Request
PGRR106 Clarify Projects Included in Transmission Project Information and Tracking (TPIT) Report
ReasonGeneral system and/or process improvement(s)
Created2023-05-04
Approved2024-09-26
Sections Affected
2.26.4.1
Summary
This Planning Guide Revision Request (PGRR) clarifies what transmission projects are included in the Transmission Project Information and Tracking (TPIT) report.
Action Log 6 milestones
-
May 4
ROSDeferred/Tabled→ Language Consideration
-
May 2
ROSRecommended for Approval→ Impact Analysis Consideration
-
Jun 6
ROSRecommended for Approval→ Revision Request Consideration
-
Jun 24
TACRecommended for Approval→ Revision Request Consideration
-
Aug 20
BOARDRecommended for Approval→ Revision Request Consideration
-
Sep 26
PUCTApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| May 2 '24 | ROS | to recommended approval of PGRR106 as amended by the 12/12/23 ERCOT comments | Passed |
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Jun 24 '24 | TAC | Motion Passes | 28 | 0 | 0 | xls |
| Jun 6 '24 | ROS | Motion Carries | 7.5 | 0 | 0 | xls |
| May 2 '24 | ROS | Motion Carries | 7.5 | 0 | 0 | xls |
| May 4 '23 | ROS | Motion Carries | 7.5 | 0 | 0 | xls |
Documents 14
| Name | Type | Posted | Classification |
|---|---|---|---|
| 106PGRR-01 Clarify Projects Included in Transmission Project Information and Tracking (TPIT) Report 041923 | docx | Apr 19 '23 | Revision Request |
| 106PGRR-02 Impact Analysis 041923 | docx | Apr 19 '23 | Staff Report |
| 106PGRR-03 ROS Ballot 050423 | xls | May 8 '23 | Revision Request Ballot |
| 106PGRR-04 ROS Report 050423 | docx | May 8 '23 | Committee Report |
| 106PGRR-05 SSWG Comments 083123 | docx | Aug 31 '23 | Revision Request Comments |
| 106PGRR-06 ERCOT Comments 121223 | docx | Dec 12 '23 | Revision Request Comments |
| 106PGRR-07 ROS Ballot 050224 | xls | May 6 '24 | Revision Request Ballot |
| 106PGRR-08 ROS Report 050224 | docx | May 6 '24 | Committee Report |
| 106PGRR-09 ROS Ballot 060624 | xls | Jun 10 '24 | Revision Request Ballot |
| 106PGRR-10 ROS Report 060624 | docx | Jun 10 '24 | Committee Report |
| 106PGRR-11 TAC Ballot 062424 | xls | Jun 25 '24 | Revision Request Ballot |
| 106PGRR-12 TAC Report 062424 | docx | Jun 25 '24 | Committee Report |
| 106PGRR-13 Board Report 082024 | docx | Aug 22 '24 | Committee Report |
| 106PGRR-14 PUCT Report 092624 | docx | Sep 30 '24 | Committee Report |
Meetings That Took It Up 23
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Aug 20 '24 | Board of Directors Meeting | BOARD | Concluded |
| Jul 16 '24 | PLWG Meeting | PLWG | Concluded |
| Jul 3 '24 | SSWG Meeting - Webex Only | SSWG | Concluded |
| Jun 24 '24 | TAC Meeting - Webex Only | TAC | Concluded |
| Jun 6 '24 | ROS Meeting | ROS | Concluded |
| Jun 5 '24 | SSWG Meeting - Webex Only | SSWG | Concluded |
| May 2 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Apr 4 '24 | ROS Meeting | ROS | Concluded |
| Apr 3 '24 | SSWG Meeting | SSWG | Concluded |
| Mar 13 '24 | SSWG Meeting - Webex Only | SSWG | Concluded |
| Mar 7 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Feb 7 '24 | SSWG Meeting - Webex Only | SSWG | Concluded |
| Feb 1 '24 | ROS Meeting - Webex Only | ROS | Concluded |
| Jan 8 '24 | ROS Meeting | ROS | Concluded |
| Dec 7 '23 | ROS Meeting - Webex Only | ROS | Concluded |
| Dec 6 '23 | SSWG Meeting - Webex Only | SSWG | Concluded |
| Nov 2 '23 | ROS Meeting | ROS | Concluded |
| Oct 5 '23 | ROS Meeting - Webex Only | ROS | Concluded |
| Sep 7 '23 | ROS Meeting | ROS | Concluded |
| Aug 3 '23 | ROS Meeting | ROS | Concluded |
| Jul 6 '23 | ROS Meeting - Webex Only | ROS | Concluded |
| Jun 8 '23 | ROS Meeting | ROS | Concluded |
| May 4 '23 | ROS Meeting - Webex Only | ROS | Concluded |