PGRR #68 · Revision Request
PGRR068 Addition of a Proposed DC Tie to the Planning Models
ReasonRegulatory requirements
Created2018-08-09
Approved2018-12-11
Sections Affected
6.12 (new)
Summary
In Public Utility Council of Texas (PUCT) Project No. 46304, the PUCT directed ERCOT to determine how to best model the Southern Cross DC Tie in its planning cases. Pursuant to that Directive, ERCOT has determined that a Planning Guide Revision Request (PGRR) is necessary to address when a new Direct Current Tie (DC Tie) should be added to the ERCOT planning models. Accordingly, this PGRR describes the process for adding a DC Tie to the models and associated requirements.
Action Log 5 milestones
-
Aug 9
ROSDeferred/Tabled→ Language Consideration
-
Sep 6
ROSRecommended for Approval→ Impact Analysis Consideration
-
Oct 11
ROSRecommended for Approval→ Revision Request Consideration
-
Nov 29
TACRecommended for Approval→ Revision Request Consideration
-
Dec 11
BOARDApproved
Documents 7
| Name | Type | Posted | Classification |
|---|---|---|---|
| 068PGRR-01 Addition of a Proposed DC Tie to the Planning Models 072518 | doc | Jul 25 '18 | Revision Request |
| 068PGRR-02 Impact Analysis 072518 | doc | Dec 4 '18 | Staff Report |
| 068PGRR-03 ROS Report 080918 | doc | Aug 10 '18 | Committee Report |
| 068PGRR-04 ROS Report 090618 | doc | Sep 11 '18 | Committee Report |
| 068PGRR-05 ROS Report 101118 | doc | Oct 16 '18 | Committee Report |
| 068PGRR-06 TAC Report 112918 | doc | Nov 30 '18 | Committee Report |
| 068PGRR-07 Board Report 121118 | doc | Dec 12 '18 | Committee Report |
Meetings That Took It Up 6
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 11 '18 | Board of Directors Meeting | BOARD | Concluded |
| Nov 29 '18 | TAC Meeting | TAC | Concluded |
| Oct 11 '18 | ROS Meeting | ROS | Concluded |
| Sep 6 '18 | ROS Meeting | ROS | Concluded |
| Aug 22 '18 | PLWG Meeting | PLWG | Concluded |
| Aug 9 '18 | ROS Meeting | ROS | Concluded |