PGRR #67 · Revision Request
PGRR067 Procedures for Wind and Solar Equipment Change
- ROS Nov 8 '18
- TAC Nov 29 '18
- BOARD Dec 11 '18
- PUCT —
ReasonAddresses current operational issues.
Created2018-07-12
Approved2018-12-11
Sections Affected
5.1.15.2.15.2.25.35.3.15.4.15.4.25.4.2.15.7.25.7.3and 5.9
Summary
This Planning Guide Revision Request (PGRR) describes how wind and solar facility equipment changes are treated throughout the generation interconnection process and clarifies language for Generation Interconnection or Change Request (GINR)-related fees.
Timeline
-
May 31
Listed without action at 1 meeting
- Jun 26
-
Jul 12
ROS ROS MeetingROSDeferred/Tabled Referred → PLWG“To table PGRR067 and refer the issue to the Planning Working Group (PLWG).” — Passed→ Language Consideration
- Jul 19
- Jul 25
- Aug 9
- Aug 16
-
Aug 22
Listed without action at 1 meeting
- Sep 6
- Sep 13
-
Sep 18
Listed without action at 1 meeting
-
Oct 11
ROS ROS MeetingROSRecommended for Approval Amended by the Sep 13 '18 ERCOT comments“To recommend approval of PGRR067 as amended by the 9/13/18 ERCOT comments as revised by ROS.” — Passed→ Impact Analysis Consideration
- Oct 18
-
Nov 8
ROS ROS MeetingROSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 10/11/18 ROS Report and Revised Impact Analysis for PGRR067.” — Passed→ Revision Request Consideration
- Nov 15
-
Nov 29
TAC TAC MeetingTACRecommended for Approval“To recommend approval of PGRR067 as recommended by ROS in the 11/8/18 ROS Report.” — Passed→ Revision Request Consideration
-
Dec 11
BOARD Board of Directors MeetingBOARDApproved“To approve PGRR67 as recommended by TAC in the 11/29/18 TAC Report.” — Passed
-
—
Posted since the last meeting