PGRR #66 · Revision Request
PGRR066 Interconnection Request Cancellation and Creation of Inactive Status
ReasonMarket efficiencies or enhancements
Created2018-07-12
Approved2018-12-11
Sections Affected
5.2.15.3.25.4.85.5.15.7.15.7.6 (new)and 5.7.7 (new)
Summary
This Planning Guide Revision Request (PGRR) creates an Inactive Status for Generation Interconnection and Change Request (GINR) projects that will not be listed in ERCOT monthly Generation Interconnection Status report but will retain the interconnection request numbers. This PGRR also defines a process that can be used to cancel interconnection requests that have failed to meet requirements.
Action Log 5 milestones
-
Jul 12
ROSDeferred/Tabled→ Language Consideration
-
Oct 11
ROSRecommended for Approval→ Impact Analysis Consideration
-
Nov 8
ROSRecommended for Approval→ Revision Request Consideration
-
Nov 29
TACRecommended for Approval→ Revision Request Consideration
-
Dec 11
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Oct 11 '18 | ROS | to recommend approval of PGRR066 as amended by the 9/12/18 ERCOT comments as revised by ROS | Passed |
Documents 9
| Name | Type | Posted | Classification |
|---|---|---|---|
| 066PGRR-01 Interconnection Request Cancellation and Creation of Inactive Status 062618 | doc | Jun 26 '18 | Revision Request |
| 066PGRR-02 Impact Analysis 062618 | doc | Jun 26 '18 | Staff Report |
| 066PGRR-03 ROS Report 071218 | doc | Jul 13 '18 | Committee Report |
| 066PGRR-04 ERCOT Comments 091218 | doc | Sep 12 '18 | Revision Request Comments |
| 066PGRR-05 ROS Report 101118 | doc | Oct 16 '18 | Committee Report |
| 066PGRR-06 ROS Report 110818 | doc | Nov 12 '18 | Committee Report |
| 066PGRR-07 PRS Comments 111518 | doc | Nov 16 '18 | Revision Request Comments |
| 066PGRR-08 TAC Report 112918 | doc | Nov 30 '18 | Committee Report |
| 066PGRR-09 Board Report 121118 | doc | Dec 12 '18 | Committee Report |
Meetings That Took It Up 12
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 30 '19 | Resource Integration Workshop | RIWG | Concluded |
| Dec 11 '18 | Board of Directors Meeting | BOARD | Concluded |
| Nov 29 '18 | TAC Meeting | TAC | Concluded |
| Nov 15 '18 | PRS Meeting | PRS | Concluded |
| Nov 8 '18 | ROS Meeting | ROS | Concluded |
| Oct 11 '18 | ROS Meeting | ROS | Concluded |
| Sep 18 '18 | PLWG Meeting | PLWG | Concluded |
| Sep 6 '18 | ROS Meeting | ROS | Concluded |
| Aug 22 '18 | PLWG Meeting | PLWG | Concluded |
| Aug 9 '18 | ROS Meeting | ROS | Concluded |
| Jul 25 '18 | PLWG Meeting | PLWG | Concluded |
| Jul 12 '18 | ROS Meeting | ROS | Concluded |