OBDRR007 Revisions to the ORDC Methodology to Include Photo-Voltaic Generation Resources (PVGRs)
ReasonAddresses current operational issues
Created2018-09-26
Approved2018-12-11
Sections Affected
Methodology for Implementing Operating Reserve Demand Curve (ORDC) to Calculate Real-Time Reserve Price Adder
Summary
Since it was implemented in June 2014, the Operating Reserve Demand Curve (ORDC) methodology specifically excludes curtailed Photo-Voltaic Generation Resources (PVGRs) in the determination of the ORDC price adders. Since that time, substantial MWs of PVGRs have been installed in ERCOT, a considerable amount of which is being curtailed on a regular basis. This Other Binding Document Revision Request (OBDRR) changes the methodology to consider the additional capacity.
Action Log 3 milestones
-
Sep 26
TACDeferred/Tabled→ TAC for consideration
-
Nov 29
TACRecommended for Approval→ Board for consideration
-
Dec 11
BOARDApproved
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 007OBDRR-01 Revisions to the ORDC Methodology to Include Photo Voltaic Generation Resources (PVGRs) 080118 | doc | Aug 1 '18 | Revision Request |
| 007OBDRR-02 Impact Analysis 080118 | doc | Aug 1 '18 | Staff Report |
| 007OBDRR-03 WMS Comments 081018 | doc | Aug 10 '18 | Revision Request Comments |
| 007OBDRR-04 TAC Report 092618 | doc | Sep 27 '18 | Committee Report |
| 007OBDRR-05 TAC Report 112918 | doc | Nov 30 '18 | Committee Report |
| 007OBDRR-06 Board Report 121118 | doc | Dec 12 '18 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 11 '18 | Board of Directors Meeting | BOARD | Concluded |
| Nov 29 '18 | TAC Meeting | TAC | Concluded |
| Sep 26 '18 | TAC Meeting | TAC | Concluded |
| Aug 8 '18 | WMS Meeting | WMS | Concluded |