NPRR #897 · Revision Request

NPRR897  Adjustments to Black Start Service (BSS) Procurement Timeline and Testing

Approved sponsor ERCOT posted 2018-08-29 ercot.com
ReasonMarket efficiencies or enhancements
Created2018-09-13
Approved2018-12-11
Sections Affected
3.14.28.1.1.2.1.522 Attachment M (new)
Summary
This Nodal Protocol Revision Request (NPRR) adjusts the timeline for the Black Start Service (BSS) procurement and testing process, adds a weather limitation disclosure form, and aligns the Load-Carrying Test procedure with actual practice.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Oct 18 '18PRS to recommend approval of NPRR897 as amended by the 10/15/18 ROS comments as revised by PRSPassed
Documents 11
NameTypePostedClassification
897NPRR-01 Adjustments to BSS Procurement Timeline and Testing 082918 doc Aug 29 '18 Revision Request
897NPRR-02 Impact Analysis 082918 doc Aug 29 '18 Staff Report
897NPRR-03 STEC Comments 090518 doc Sep 5 '18 Revision Request Comments
897NPRR-04 STEC Comments 091418 docx Sep 14 '18 Revision Request Comments
897NPRR-05 PRS Report 091318 doc Sep 17 '18 Committee Report
897NPRR-06 ROS Comments 101518 docx Oct 15 '18 Revision Request Comments
897NPRR-07 PRS Report 101818 docx Oct 23 '18 Committee Report
897NPRR-08 PRS Report 111518 docx Nov 16 '18 Committee Report
897NPRR-09 ERCOT Comments 111918 doc Nov 19 '18 Revision Request Comments
897NPRR-10 TAC Report 112918 docx Nov 30 '18 Committee Report
897NPRR-11 Board Report 121118 docx Dec 11 '18 Committee Report
Meetings That Took It Up 6
DateMeetingCommitteeStatus
Dec 11 '18 Board of Directors Meeting BOARD Concluded
Nov 29 '18 TAC Meeting TAC Concluded
Nov 15 '18 PRS Meeting PRS Concluded
Oct 18 '18 PRS Meeting PRS Concluded
Oct 11 '18 ROS Meeting ROS Concluded
Sep 13 '18 PRS Meeting PRS Concluded