NPRR #879 · Revision Request
NPRR879 SCED Base Point, Base Point Deviation, and Performance Evaluation Changes for IRRs that Carry Ancillary Services
ReasonAddresses current operational issues
Created2018-06-14
Approved2018-12-11
Sections Affected
6.5.7.26.6.5.1.1.16.6.5.1.1.26.6.5.1.1.36.6.5.1.1.46.6.5.2and 8.1.1.4.1
Summary
This Nodal Protocol Revision Request (NPRR) proposes that Intermittent Renewable Resources (IRRs) carrying Ancillary Service Resource Responsibilities receive a Security-Constrained Economic Dispatch (SCED) Base Point calculated using the five-minute intra-hour forecast of the Resource. Generation Resource Energy Deployment Performance (GREDP) metrics are added to score performance during these intervals. Base Point Deviation Charges are adjusted to treat IRRs providing Ancillary Services the same as conventional generators. These changes cannot be done manually and will be active once a system change is implemented. This NPRR contains clean-up changes to correct the unit of measure for some billing determinants, and an as-built correction to the Settlement equation in paragraph (4) of Section 6.6.5.2. These clean-up changes do not introduce any system impact or Settlement changes. This NPRR also contains administrative edits to paragraphs (7) - (9) of Section 8.1.1.4.1, to align the paragraph numbering with current Protocol formatting style. These edits are authored as “ERCOT Market Rules” in this NPRR.
Action Log 5 milestones
-
Jun 14
PRSDeferred/Tabled→ Language Consideration
-
Sep 13
PRSRecommended for Approval→ PRS for Impact Analysis review
-
Oct 18
PRSRecommended for Approval→ TAC for consideration
-
Nov 29
TACRecommended for Approval→ Board for consideration
-
Dec 11
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Sep 13 '18 | PRS | To recommend approval of NPRR879 as amended by the 8/3/18 ERCOT comments as revised by PRS | Passed |
| Oct 18 '18 | PRS | To endorse and forward to TAC the 9/13/18 PRS Report as amended by the 9/25/18 ERCOT comments and the Revised Impact Analysis for NPRR879 with a recommended priority of 2020 and rank of 2800 | Passed |
Documents 14
| Name | Type | Posted | Classification |
|---|---|---|---|
| 879NPRR-01 SCED Base Point and Performance Evaluation Changes for IRRs that Carry Ancillary Service 053018 | doc | May 30 '18 | Revision Request |
| 879NPRR-02 Impact Analysis 053018 | doc | May 30 '18 | Staff Report |
| 879NPRR-03 PRS Report 061418 | doc | Jun 14 '18 | Committee Report |
| 879NPRR-04 WMS Comments 071218 | doc | Jul 12 '18 | Revision Request Comments |
| 879NPRR-05 ROS Comments 071318 | doc | Jul 13 '18 | Revision Request Comments |
| 879NPRR-06 ERCOT Comments 080318 | doc | Aug 3 '18 | Revision Request Comments |
| 879NPRR-07 ROS Comments 080918 | doc | Aug 9 '18 | Revision Request Comments |
| 879NPRR-08 WMS Comments 090618 | doc | Sep 6 '18 | Revision Request Comments |
| 879NPRR-09 PRS Report 091318 | doc | Sep 19 '18 | Committee Report |
| 879NPRR-10 ERCOT Comments 092518 | doc | Sep 25 '18 | Revision Request Comments |
| 879NPRR-11 Revised Impact Analysis 101018 | doc | Oct 10 '18 | Staff Report |
| 879NPRR-12 PRS Report 101818 | doc | Oct 23 '18 | Committee Report |
| 879NPRR-13 TAC Report 112918 | doc | Nov 30 '18 | Committee Report |
| 879NPRR-14 Board Report 121118 | doc | Dec 11 '18 | Committee Report |
Meetings That Took It Up 15
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 11 '18 | Board of Directors Meeting | BOARD | Concluded |
| Nov 29 '18 | TAC Meeting | TAC | Concluded |
| Oct 18 '18 | PRS Meeting | PRS | Concluded |
| Sep 13 '18 | PRS Meeting | PRS | Concluded |
| Sep 5 '18 | WMS Meeting | WMS | Concluded |
| Aug 27 '18 | QMWG Meeting | QMWG | Concluded |
| Aug 16 '18 | PRS Meeting | PRS | Concluded |
| Aug 13 '18 | QMWG Meeting | QMWG | Concluded |
| Aug 9 '18 | ROS Meeting | ROS | Concluded |
| Aug 8 '18 | WMS Meeting | WMS | Concluded |
| Jul 19 '18 | PRS Meeting | PRS | Concluded |
| Jul 17 '18 | PDCWG Meeting | PDCWG | Concluded |
| Jul 12 '18 | ROS Meeting | ROS | Concluded |
| Jul 11 '18 | WMS Meeting | WMS | Concluded |
| Jun 14 '18 | PRS Meeting | PRS | Concluded |