NPRR779  Clarifies References to Texas Reliability Entity and Independent Market Monitor

Approved sponsor ERCOT posted 2016-05-27 ercot.com
ReasonThis NPRR aligns the ERCOT Nodal Protocols with current regulatory requirements.
Created2016-06-16
Approved2016-10-11
Sections Affected
2.18.1.1.38.1.1.48.1.1.4.28.1.1.4.321.121.121.321.4.421.4.521.4.11.121.4.11.221.4.11.3
Summary
This Nodal Protocol Revision Request (NPRR) clarifies references to the Texas Reliability Entity (Texas RE) and the Independent Market Monitor (IMM). The Nodal Protocols currently refer to the Texas Reliability Entity in both its capacity as the North American Electric Reliability Corporation (NERC) Regional Entity and the Public Utility Commission of Texas (PUCT) Reliability Monitor, a new term recently added to P.U.C SUBST. R. § 25.503, Oversight of Wholesale Market Participants. This NPRR modifies uses of the term “Texas Reliability Entity” to more accurately reflect distinct references to the NERC Regional Entity and the PUCT Reliability Monitor, and introduces the defined term “Reliability Monitor” per P.U.C SUBST. R. § 25.503. This NPRR also removes the 24-hour deadline by which ERCOT must notify the Reliability Monitor of a failure to provide Ancillary Services, and clarifies that the IMM is an included party in several provisions related to the ERCOT stakeholder process.
Action Log 5 milestones
Documents 7
NameTypePostedClassification
779NPRR-01 Clarifies References to Texas Reliability Entity and IMM 052716 docx May 27 '16 Revision Request
779NPRR-02 Impact Analysis 052716 doc May 27 '16 Staff Report
779NPRR-03 PRS Report 061616 doc Jun 17 '16 Committee Report
779NPRR-04 PRS Report 071416 doc Jul 19 '16 Committee Report
779NPRR-05 TAC Report 072816 doc Jul 29 '16 Committee Report
779NPRR-06 TAC Report 082516 doc Aug 30 '16 Committee Report
779NPRR-07 Board Report 101116 doc Oct 11 '16 Committee Report
Meetings That Took It Up 13
DateMeetingCommitteeStatus
Oct 27 '16 TAC Meeting TAC Concluded
Oct 11 '16 Board of Directors Meeting BOARD Concluded
Sep 29 '16 TAC Meeting TAC Concluded
Aug 25 '16 TAC Meeting TAC Concluded
Aug 4 '16 ROS Meeting ROS Concluded
Jul 28 '16 TAC Meeting TAC Concluded
Jul 21 '16 OWG Meeting OWG Concluded
Jul 20 '16 PLWG Meeting PLWG Concluded
Jul 14 '16 PRS Meeting PRS Concluded
Jun 29 '16 PLWG Meeting PLWG Concluded
Jun 23 '16 OWG Meeting OWG Concluded
Jun 22 '16 CWG/MCWG Meeting CREDITWG Concluded
Jun 16 '16 PRS Meeting PRS Concluded