NPRR #753 · Revision Request
NPRR753 Allow AMS Data Submittal Process for TDSP-Read Non-Modeled Generators
- PRS Aug 11 '16
- TAC Aug 25 '16
- BOARD Oct 11 '16
- PUCT —
ReasonAddresses current operational issues. Market efficiencies/enhancements
Created2016-02-11
Approved2016-10-11
Sections Affected
1.3.1.1 and 10.9
Summary
This Nodal Protocol Revision Request (NPRR) allows the option of using the Advanced Metering System (AMS) data submittal process for all Transmission and/or Distribution Provider (TDSP)-read Non-Modeled Generators; and requires an Interval Data Recorder (IDR) Meter for Block Load Transfer (BLT) metering points registered for Settlements in accordance with Section 6.5.9.5.1, Registration and Posting of BLT Points.
Timeline
- Jan 26
-
Feb 2
Listed without action at 2 meetings (Feb 2 '16 – Feb 10 '16)
-
Feb 11
PRS PRS MeetingPRSDeferred/Tabled Referred → RMS“To table NPRR753 and refer the issue to RMS” — Passed→ PRS for consideration
- Mar 1
- Mar 10
- Apr 5
-
Apr 14
Listed without action at 1 meeting
- May 3
-
May 12
PRS PRS MeetingPRSRecommended for Approval Amended by the Feb 29 '16 ERCOT comments“To recommend approval of NPRR753 as amended by the 2/29/16 ERCOT comments” — Passed→ PRS for Impact Analysis review
- May 18
- Jun 7
-
Jun 16
PRS PRS MeetingPRSDeferred/Tabled“To table NPRR753 for one month” — Passed→ PRS for Impact Analysis review
- Jul 14
- Aug 2
-
Aug 11
PRS PRS MeetingPRSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 7/14/16 PRS Report and Impact Analysis for NPRR753” — Passed→ TAC for consideration
-
Aug 25
TAC TAC MeetingTACRecommended for Approval“To recommend approval of NPRR753 as recommended by PRS in the 8/11/16 PRS Report” — Passed→ Board for consideration
-
Oct 11
BOARD Board of Directors MeetingBOARDApproved“To approve NPRR753 as recommended by TAC in the 8/25/16 TAC Report” — Passed
-
Jan 10
Listed without action at 2 meetings (Jan 10 '17 – Mar 28 '17)