NPRR705  Provides Consistency for References to the End Date of the Generation Interconnection Process

Approved sponsor ERCOT posted 2015-05-20 ercot.com
ReasonAdministrative
Created2015-06-11
Approved2015-12-08
Sections Affected
1.3.1.21.3.32.13.154.4.9.4.1
Summary
In the Resource Interconnection Handbook, the term “commercial operations” has a different meaning to Resource Entities and financial institutions involved in construction and financing of Generation Resources than it does in the context of performance testing by ERCOT for new Generation Resources. This Nodal Protocol Revision Request (NPRR) replaces various terms used to refer to the date on which Generation Resources complete the Resource interconnection process with the proposed defined terms “Commercial Operations Date” and “Resource Commissioning Date” to provide consistency for references to the end of the generation interconnection process.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Oct 15 '15PRS To recommend approval of NPRR705 as amended by the 10/12/15 ROS comments.Passed
Nov 12 '15PRS To endorse and forward to TAC the 10/15/15 PRS Report and revised Impact Analysis for NPRR705.Passed
Nov 19 '15TAC To recommend approval of NPRR705 as recommended by PRS in the 11/12/15 PRS Report and as amended by the 11/13/15 ERCOT comments.Passed
Documents 12
NameTypePostedClassification
705NPRR-01 Provides Consistency for References to the End Date of the Generation Interconnection Process 052015 doc Jun 11 '15 Revision Request
705NPRR-02 Impact Analysis 052015 doc May 20 '15 Staff Report
705NPRR-03 PRS Report 061115 doc Jun 15 '15 Committee Report
705NPRR-04 Luminant Comments 070615 doc Jul 6 '15 Revision Request Comments
705NPRR-05 WMS Comments 080615 doc Aug 6 '15 Revision Request Comments
705NPRR-06 ROS Comments 101215 doc Oct 12 '15 Revision Request Comments
705NPRR-07 PRS Report 101515 doc Oct 16 '15 Committee Report
705NPRR-08 Revised Impact Analysis 103015 doc Oct 30 '15 Staff Report
705NPRR-09 PRS Report 111215 doc Nov 13 '15 Committee Report
705NPRR-10 ERCOT Comments 111315 doc Nov 13 '15 Revision Request Comments
705NPRR-11 TAC Report 111915 doc Nov 20 '15 Committee Report
705NPRR-12 Board Report 120815 doc Dec 8 '15 Committee Report
Meetings That Took It Up 23
DateMeetingCommitteeStatus
Dec 8 '15 Board of Directors Meeting BOARD Concluded
Nov 19 '15 TAC Meeting TAC Concluded
Nov 12 '15 PRS Meeting PRS Concluded
Nov 5 '15 ROS Informational Session - WebEx Only ROS Concluded
Oct 29 '15 TAC Meeting TAC Concluded
Oct 21 '15 CWG/MCWG Meeting CREDITWG Concluded
Oct 15 '15 PRS Meeting PRS Concluded
Oct 8 '15 ROS Meeting ROS Concluded
Sep 17 '15 OWG Meeting OWG Concluded
Sep 15 '15 PLWG Meeting PLWG Concluded
Sep 10 '15 PRS Meeting PRS Concluded
Sep 3 '15 ROS Meeting ROS Concluded
Aug 20 '15 OWG Meeting OWG Concluded
Aug 13 '15 PRS Meeting PRS Concluded
Aug 5 '15 WMS Meeting WMS Concluded
Jul 23 '15 OWG Meeting OWG Concluded
Jul 22 '15 PLWG Meeting PLWG Concluded
Jul 16 '15 PRS Meeting PRS Concluded
Jul 14 '15 RDWG Meeting RDWG Concluded
Jul 9 '15 ROS Meeting ROS Concluded
Jul 8 '15 WMS Meeting WMS Concluded
Jun 16 '15 RDWG Meeting RDWG Concluded
Jun 11 '15 PRS Meeting PRS Concluded