NPRR #528 · Revision Request

NPRR528  Clarification of Assessment of Chronic Congestion

Approved sponsor ERCOT posted 2013-03-06 ercot.com
ReasonRemoves duplicate requirements and clarifies ERCOT’s responsibilities.
Created2013-03-21
Approved2013-12-10
Sections Affected
3.10.43.11.53.206.5.7.1.11
Summary
This Nodal Protocol Revision Request (NPRR) consolidates into one section, the steps ERCOT will take when active or binding transmission constraints are identified.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Sep 19 '13PRS To recommend approval of NPRR528 as amended by the 9/16/13 ROS comments and as revised by PRSPassed
Documents 23
NameTypePostedClassification
528NPRR-01 Clarification of Assessment of Chronic Congestion 030 doc Mar 6 '13 Revision Request
528NPRR-02 Impact Analysis 030613 doc Mar 6 '13 Staff Report
528NPRR-03 PRS Report 032113 doc Mar 26 '13 Committee Report
528NPRR-04 ROS Comments 041513 doc Apr 15 '13 Revision Request Comments
528NPRR-05 Luminant Comments 041513 doc Apr 15 '13 Revision Request Comments
528NPRR-06 Oncor Comments 043013 doc Apr 30 '13 Revision Request Comments
528NPRR-07 ERCOT Comments 051513 doc May 15 '13 Revision Request Comments
528NPRR-08 Luminant Energy Comments 062713 doc Jun 27 '13 Revision Request Comments
528NPRR-09 OWG Comments 070213 doc Jul 2 '13 Revision Request Comments
528NPRR-10 Luminant Energy Comments 070913 doc Jul 9 '13 Revision Request Comments
528NPRR-11 ERCOT Comments 071013 doc Jul 10 '13 Revision Request Comments
528NPRR-12 WMS Comments 071213 doc Jul 12 '13 Revision Request Comments
528NPRR-13 ROS Comments 071513 doc Jul 15 '13 Revision Request Comments
528NPRR-14 OWG Comments 072213 doc Jul 22 '13 Revision Request Comments
528NPRR-15 Edison Mission Marketing & Trading 081313 doc Aug 13 '13 Revision Request Comments
528NPRR-16 ROS Comments 081913 doc Aug 19 '13 Revision Request Comments
528NPRR-17 Constraint Management Plan Revision Request Workshop doc Sep 9 '13 Revision Request Comments
528NPRR-18 WMS Comments 091113 doc Sep 11 '13 Revision Request Comments
528NPRR-19 ROS Comments 091613 doc Sep 16 '13 Revision Request Comments
528NPRR-20 PRS Report 091913 doc Sep 23 '13 Committee Report
528NPRR-21 PRS Report 101713 doc Oct 21 '13 Committee Report
528NPRR-22 TAC Report 110713 doc Nov 8 '13 Committee Report
528NPRR-23 Board Report 121013 doc Dec 11 '13 Committee Report
Meetings That Took It Up 28
DateMeetingCommitteeStatus
Dec 10 '13 Board of Directors Meeting BOARD Concluded
Nov 7 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
Oct 17 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Sep 25 '13 Joint Credit Working Group (CWG)/Market Credit Working Group (MCWG) Meeting CREDITWG Concluded
Sep 19 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Sep 12 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Sep 11 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Sep 6 '13 Workshop - Constraint Management Plan Revision Requests Concluded
Sep 3 '13 Workshop - Constraint Management Plan Revision Requests Concluded
Aug 22 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Aug 15 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Aug 14 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Jul 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jul 17 '13 Operations Working Group (OWG) Meetings OWG Concluded
Jul 11 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Jul 10 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Jun 27 '13 Operations Working Group (OWG) Meetings OWG Concluded
Jun 20 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Jun 19 '13 Operations Working Group (OWG) Meetings OWG Concluded
Jun 12 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
May 16 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
May 15 '13 Operations Working Group (OWG) Meetings OWG Concluded
May 6 '13 ERCOT NPRR528, NPRR529 & NOGRR110 Workshop Concluded
Apr 18 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Apr 17 '13 Operations Working Group (OWG) Meetings OWG Concluded
Apr 12 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Apr 11 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Mar 21 '13 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded