NPRR #313 · Revision Request
NPRR313 Revisions to the Resource Plan Reference to Current Operating Plan for EILS and Synchronous Condensers and Black Start Notification Requirements (formerly "Updating the Term Resource Plan to Current Operating Plan")
ReasonThe term "Resource Plan" was proper for use in the zonal Protocols; however, that term is no longer appropriate for use in the Nodal Protocols. It has been replaced by the term "Current Operating Plan". This NPRR also improves the Black Start availability reporting process.
Created2011-03-24
Sections Affected
2.13.14.34.322Attachment DAttachment F
Summary
This Nodal Protocol Revision Request (NPRR) replaces the term "Resource Plan" with the term "Current Operating Plan" or "Availability Plan" in those instances where the change in terminology was not previously made. This NPRR also proposes adding a Black Start capable status indicator to the Availability Plan to allow ERCOT to settle payment for Black Start units programmatically; and allows Qualified Scheduling Entities (QSEs) with Black Start units to provide all of the Black Start availability through the Availability Plan.
Action Log 6 milestones
-
Mar 24
PRSRecommended for Approval→ PRS review the IA.
-
Apr 21
PRSDeferred/Tabled→ PRS consideration
-
May 19
PRSRecommended for Approval→ PRS consider the IA and CBA
-
Jun 23
PRSRecommended for Approval→ TAC consideration
-
Jul 7
TACRecommended for Approval→ ERCOT Board consideration
-
Aug 16
BODNOMApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Mar 24 '11 | PRS | To recommend approval of NPRR313 as amended by Luminant Energy comments and as revised by PRS. | Passed |
| May 19 '11 | PRS | To recommend approval of the 3/24/11 PRS Report as amended by the 5/17/11 Luminant comments and as revised by PRS and to bring NPRR313 back to PRS for consideration of the Impact Analysis. | Passed |
| Jun 23 '11 | PRS | To endorse and forward the 5/19/11 PRS Report as amended by the 6/22/11 ERCOT comments and as revised by PRS and the Impact Analysis for NPRR313 to TAC with a recommended priority of High and a rank of 30. | Passed |
| Aug 16 '11 | BODNOM | To approve NPRR313 as recommended by TAC in the 7/7/11 TAC Report and as amended by the 8/5/11 ERCOT comments. | Passed |
Documents 18
| Name | Type | Posted | Classification |
|---|---|---|---|
| 313NPRR-01 Updating the Term Resource Plan to Current Operating | doc | Feb 1 '11 | Revision Request |
| 313NPRR-02 Luminant Energy Comments 032111 | doc | Mar 21 '11 | Revision Request Comments |
| 313NPRR-03 PRS Report 032411 | doc | Mar 29 '11 | Committee Report |
| 313NPRR-04 ERCOT Comments 040411 | doc | Apr 4 '11 | Revision Request Comments |
| 313NPRR-05 Impact Analysis 041211 | doc | Apr 12 '11 | Staff Report |
| 313NPRR-06 Luminant Energy Comments 041811 | doc | Apr 18 '11 | Revision Request Comments |
| 313NPRR-07 PRS Report 042111 | doc | Apr 26 '11 | Committee Report |
| 313NPRR-08 Luminant Comments 051711 | doc | May 17 '11 | Revision Request Comments |
| 313NPRR-09 ERCOT Comments 051811 | doc | May 18 '11 | Revision Request Comments |
| 313NPRR-10 PRS Report 051911 | doc | May 24 '11 | Committee Report |
| 313NPRR-11 ERCOT Comments 062211 | doc | Jun 29 '11 | Revision Request Comments |
| 313NPRR-12 Luminant Energy Comments 062211 | doc | Jun 22 '11 | Revision Request Comments |
| 313NPRR-13 PRS Report 062311 | doc | Jul 1 '11 | Committee Report |
| 313NPRR-14 Revised Impact Analysis 063011 | doc | Jun 29 '11 | Staff Report |
| 313NPRR-15 Cost Benefit Analysis 063011 | xls | Jun 30 '11 | Committee Report |
| 313NPRR-16 TAC Report 070711 | doc | Jul 11 '11 | Committee Report |
| 313NPRR-17 ERCOT Comments 080511 | doc | Aug 5 '11 | Revision Request Comments |
| 313NPRR-18 Board Report 081611 | doc | Aug 16 '11 | Committee Report |
Meetings That Took It Up 12
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 4 '12 | Qualified Scheduling Entity Managers Working Group (QMWG) Meeting | QMWG | Concluded |
| Nov 5 '12 | Qualified Scheduling Entity Managers Working Group (QMWG) Meeting | QMWG | Concluded |
| Oct 10 '12 | Wholesale Market Subcommittee (WMS) Meeting | WMS | Concluded |
| Oct 8 '12 | Qualified Scheduling Entity Managers Working Group (QMWG) Meeting | QMWG | Concluded |
| Sep 12 '12 | Wholesale Market Subcommittee (WMS) Meeting | WMS | Concluded |
| Sep 10 '12 | Qualified Scheduling Entity Managers Working Group (QMWG) Meeting | QMWG | Concluded |
| Aug 16 '11 | Board of Directors Meeting | BOARD | Concluded |
| Jul 7 '11 | TAC Meeting | TAC | Concluded |
| Jun 23 '11 | PRS Meeting | PRS | Concluded |
| May 19 '11 | PRS Meeting | PRS | Concluded |
| Apr 21 '11 | PRS Meeting | PRS | Concluded |
| Mar 24 '11 | PRS Meeting | PRS | Concluded |