NPRR #309 · Revision Request
NPRR309 Providing STWPF to QSEs Contractually Affiliated with WGR
ReasonBy receiving the WGR forecast directly from ERCOT, a QSE that purchases power from a WGR will be able to process the data in a timelier manner.
Created2011-02-17
Rejected2011-06-23
Sections Affected
4.2.2
Summary
The Nodal Protocols currently enable a Wind-powered Generation Resource (WGR) and the Qualified Scheduling Entity (QSE) representing that WGR to receive ERCOT’s Short-Term Wind Power Forecast (STWPF) for that WGR via the Messaging System and the Market Information System (MIS) Certified Area. This Nodal Protocol Revision Request (NPRR) would require ERCOT to provide the WGR forecast to any QSE contractually affiliated with that WGR.
Action Log 3 milestones
-
Feb 17
PRSReferred→ WMS consideration of NPRR309
-
May 19
PRSRecommended for Approval→ PRS Impact Analysis review
-
Jun 23
PRSRejected
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 309NPRR-01 Providing STWPF to QSEs Contractually Affiliated with | doc | Jan 14 '11 | Revision Request |
| 309NPRR-02 PRS Report 021711 | doc | Feb 21 '11 | Committee Report |
| 309NPRR-03 WMS Comments 051211 | doc | May 12 '11 | Revision Request Comments |
| 309NPRR-04 PRS Report 051911 | doc | May 20 '11 | Committee Report |
| 309NPRR-05 Impact Analysis 061711 | doc | Jun 17 '11 | Staff Report |
| 309NPRR-06 PRS Report 062311 | doc | Jun 27 '11 | Committee Report |
Meetings That Took It Up 9
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 7 '11 | TAC Meeting | TAC | Concluded |
| Jun 23 '11 | PRS Meeting | PRS | Concluded |
| May 19 '11 | PRS Meeting | PRS | Concluded |
| May 11 '11 | WMS Meeting | WMS | Concluded |
| May 9 '11 | QMWG Meeting | QMWG | Concluded |
| Apr 8 '11 | WMS Meeting | WMS | Concluded |
| Mar 24 '11 | PRS Meeting | PRS | Concluded |
| Mar 9 '11 | WMS Meeting | WMS | Concluded |
| Feb 17 '11 | PRS Meeting | PRS | Concluded |