NPRR #1272 · Revision Request
NPRR1272 Voltage Support at Private Use Networks
ReasonGeneral system and/or process improvement(s)
Created2025-03-12
Sections Affected
3.15
Summary
This Nodal Protocol Revision Request (NPRR) clarifies that Section 3.15 should be applied to require ERCOT to independently evaluate the Reactive Power requirements of Generation Resources excluding the effects of co-located retail load. As such, any Generation Resources that meet the requirements of the Protocols as standalone Generation Resources shall not have additional Reactive Power requirements imposed as a result of co-locating with load. Further, the language clarifies that the onsite load must also comply with the power factor requirements for retail Customers in the applicable tariff for retail delivery service.
Action Log 1 milestones
-
Mar 12
PRSDeferred/Tabled→ Language Consideration
Ballots
| Date | Body | Result | Yes | No | Abstain | |
|---|---|---|---|---|---|---|
| Apr 3 '25 | ROS | Motion Carries | 7.5 | 0 | 0 | xls |
| Mar 12 '25 | PRS | Motion Carries | 7 | 0 | 0 | xls |
Documents 7
| Name | Type | Posted | Classification |
|---|---|---|---|
| 1272NPRR-01 Voltage Support at Private Use Networks 020525 | docx | Feb 5 '25 | Revision Request |
| 1272NPRR-02 PRS Ballot 031225 | xls | Mar 16 '25 | Revision Request Ballot |
| 1272NPRR-03 PRS Report 031225 | docx | Mar 16 '25 | Committee Report |
| 1272NPRR-04 ROS Ballot 040325 | xls | Apr 4 '25 | Revision Request Ballot |
| 1272NPRR-05 ROS Comments 040425 | docx | Apr 4 '25 | Revision Request Comments |
| 1272NPRR-06 ERCOT Comments 042925 | docx | Apr 29 '25 | Revision Request Comments |
| 1272NPRR-07 Oxy Comments 052025 | doc | May 20 '25 | Revision Request Comments |
Meetings That Took It Up 36
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jul 15 '26 | PRS Meeting | PRS | Scheduled |
| Jul 9 '26 | ROS Meeting - Webex Only | ROS | Concluded |
| Jun 10 '26 | PRS Meeting | PRS | Concluded |
| Jun 4 '26 | ROS Meeting | ROS | Concluded |
| May 7 '26 | ROS Meeting | ROS | Concluded |
| May 6 '26 | PRS Meeting | PRS | Concluded |
| Apr 15 '26 | PRS Meeting | PRS | Concluded |
| Apr 2 '26 | ROS Meeting | ROS | Concluded |
| Mar 11 '26 | PRS Meeting | PRS | Concluded |
| Mar 5 '26 | ROS Meeting | ROS | Concluded |
| Feb 11 '26 | PRS Meeting | PRS | Concluded |
| Feb 5 '26 | ROS Meeting | ROS | Concluded |
| Jan 14 '26 | PRS Meeting | PRS | Concluded |
| Jan 8 '26 | ROS Meeting | ROS | Concluded |
| Dec 10 '25 | PRS Meeting | PRS | Concluded |
| Dec 4 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Nov 12 '25 | PRS Meeting | PRS | Concluded |
| Nov 6 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Oct 8 '25 | PRS Meeting | PRS | Concluded |
| Oct 2 '25 | ROS Meeting | ROS | Concluded |
| Sep 17 '25 | PRS Meeting | PRS | Concluded |
| Sep 11 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Aug 13 '25 | PRS Meeting | PRS | Concluded |
| Aug 7 '25 | ROS Meeting | ROS | Concluded |
| Jul 16 '25 | PRS Meeting | PRS | Concluded |
| Jul 10 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Jun 11 '25 | PRS Meeting | PRS | Concluded |
| Jun 5 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| May 14 '25 | PRS Meeting | PRS | Concluded |
| May 6 '25 | VPWG Meeting - Webex Only | VPWG | Concluded |
| May 1 '25 | ROS Meeting | ROS | Concluded |
| Apr 9 '25 | PRS Meeting | PRS | Concluded |
| Apr 3 '25 | ROS Meeting - Webex Only | ROS | Concluded |
| Mar 12 '25 | PRS Meeting | PRS | Concluded |
| Mar 6 '25 | ROS Meeting | ROS | Concluded |
| Feb 12 '25 | PRS Meeting | PRS | Concluded |