NOGRR223  Add Phasor Measurement Recording Equipment Requirement to Modified Generating Facilities in Interconnection Process

Approved sponsor ERCOT posted 2021-02-09 ercot.com
ReasonAddresses current operational issues
Created2021-03-04
Approved2021-10-07
Sections Affected
6.1.3.2
Summary
This Nodal Operating Guide Revision Request (NOGRR) adds the requirement to have phasor measurement recording equipment at existing facilities that have an aggregated generating capacity above 20 MVA at a single site following any modification that is described in paragraph (1)(b) of Planning Guide Section 5.1.1, Applicability, in order to enter the Generation Resource Interconnection or Change Request process.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Aug 5 '21ROS to recommend approval of NOGRR223 as amended by the 6/10/21 ERCOT commentsPassed
Sep 2 '21ROS to endorse and forward to TAC the 8/5/21 ROS Report and the Revised Impact Analysis for NOGRR223Passed
Sep 29 '21TAC to recommend approval of NOGRR223 as recommended by ROS in the 9/2/21 ROS Report as revised by TACPassed
Ballots
DateBodyResultYesNoAbstain
Sep 29 '21 TAC Motion Passes 27 1 2 xls
Sep 2 '21 ROS Motion Carries 7.5 0 0 xls
Aug 5 '21 ROS Motion Carries 4.5 0 13 xls
Feb 1 '04 ROS Motion Carries 7.5 0 0 xls
Documents 14
NameTypePostedClassification
223NOGRR-01 Add Phasor Measurement Recording Equipment Requirement to Modified Generating Facilities in Interconnection Process 020921 doc Feb 9 '21 Revision Request
223NOGRR-02 Impact Analysis 020921 docx Feb 9 '21 Staff Report
223NOGRR-03 ROS Ballot 030421 xls Mar 5 '21 Revision Request Ballot
223NOGRR-04 ROS Report 030421 doc Mar 5 '21 Committee Report
223NOGRR-05 Luminant Comments 052621 doc May 26 '21 Revision Request Comments
223NOGRR-06 ERCOT Comments 061021 doc Jun 10 '21 Revision Request Comments
223NOGRR-07 Revised Impact Analysis 080421 docx Aug 4 '21 Staff Report
223NOGRR-08 ROS Ballot 080521 xls Aug 10 '21 Revision Request Ballot
223NOGRR-09 ROS Report 080521 doc Aug 10 '21 Committee Report
223NOGRR-10 ROS Ballot 090221 xls Sep 8 '21 Revision Request Ballot
223NOGRR-11 ROS Report 090221 doc Sep 8 '21 Committee Report
223NOGRR-12 TAC Ballot 092921 xls Sep 29 '21 Revision Request Ballot
223NOGRR-13 TAC Report 092921 doc Sep 29 '21 Committee Report
223NOGRR-14 PUCT Report 100721 doc Oct 8 '21 Committee Report
Meetings That Took It Up 13
DateMeetingCommitteeStatus
Sep 29 '21 TAC Meeting by Webex Only TAC Concluded
Sep 2 '21 ROS Meeting by Webex Only ROS Concluded
Aug 5 '21 ROS Meeting by Webex Only ROS Concluded
Jul 13 '21 OWG Meeting by Webex Only OWG Concluded
Jul 8 '21 ROS Meeting by Webex Only ROS Concluded
Jun 17 '21 OWG Meeting by Webex Only OWG Concluded
Jun 3 '21 ROS Meeting by Webex Only ROS Concluded
May 27 '21 OWG Meeting by Webex Only OWG Concluded
Apr 29 '21 ROS Meeting by Webex Only ROS Concluded
Apr 16 '21 OWG Meeting by Webex Only OWG Concluded
Apr 1 '21 ROS Meeting by Webex Only ROS Concluded
Mar 18 '21 OWG Meeting by Webex Only OWG Concluded
Mar 4 '21 ROS Meeting by Webex Only ROS Concluded