Meeting · LFLTF
LFLTF Meeting
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 Room A and B
VirtualWebEx / Teams
Dial-in877-668-4493
Revision Requests On The Agenda
Agenda 5 items
- 1. Welcome and Antitrust Admonition — Bob Wittmeyer
- 2. ERCOT History of New Design Topics — Bob Wittmeyer
- 3. Queue Update Posted — Agee Springer
-
4.
Responses to Stakeholder Questions and Comments New Large Load Interconnection Process RCL Registration and Deployment Ramp Rate Restrictions Registration of Loads 25 MW and greater
— ERCOT Staff
- 1191 GSEC Comments · Revision Request Comments
- Informal Comments on NPRR 1191 and Associated RRs from Lancium 082823 · Revision Request Comments
- 082311 CPS Comments to NPRR1191 Lg Load Registration · Revision Request Comments
- AEP High Level Comments 8-28-2023 · Revision Request Comments
- Satoshi NPRR1191 Informal Comments · Revision Request Comments
- 1191NPRR-03 Oncor Comments 082523 · Revision Request Comments
- 1191NPRR-04 TIEC Comments 082823 · Revision Request Comments
- PUBLIC 9 6 LFLTF RR Comments · Revision Request Comments
- 5. Overview of Topics for 9/25 LFLTF New Load Interconnection Process Ramp Rate Restrictions Voltage Ride-Through Other topics as identified during the meeting
Documents 8
| Name | Doc Type | Type | Posted |
|---|---|---|---|
| July 2023 LLI Queue Status Update | Aug 9 '23 | ||
| TBC Comments on 1191NPRR and 256NOGRR | Aug 28 '23 | ||
| Priority Power Management - Comments and Concerns on Proposed ERCOT NPRR1191 - NOGRR256 - PGRR111 - 8-28-2023 | Aug 29 '23 | ||
| TXOGA NPRR 1191 Comments 8.28 | Aug 29 '23 | ||
| ERCOT Steel Mills Business Function Comments on NPRR 1191 final | Aug 29 '23 | ||
| NPRR 1191 Comments | Aug 29 '23 | ||
| Galaxy comments on 1191NPRR | Aug 31 '23 | ||
| LLI Queue Status Update - 2023-09-06 | Sep 6 '23 |