Meeting · OWG
OWG Meeting
LocationERCOT Austin 8000 Metropolis (Building E), Suite 100 Austin, TX 78744 Room 206B
Revision Requests On The Agenda
Agenda 13 items
- 1. Antitrust Admonition — Owens · 9:30 am
- 2. ROS Meeting Report no new assignments — Owens
-
3.
OWG meeting notes approval: April meeting notes review and approval.
— All
- OWG_MeetingNotes_042314 · Meeting Minutes
- 4. NOGRRs for review and language changes: 129NOGRR Implement Operational Preparedness for Geomagnetic Disturbances. This NOGRR sets up a process through which ERCOT and Transmission Service Providers (TSPs) will develop Geomagnetic Disturbance (GMD) Operating Plans that will be coordinated across the ERCOT Region and provides for communication of information regarding those Plans. (GMDTF) IA Review 131NOGRR Clarification for generation Resources During an EEA. This Nodal Operating Guide Revision Request (NOGRR) clarifies language that when ERCOT is in an Energy Emergency Alert (EEA), Qualified Scheduling Entities (QSEs) must receive authorization from ERCOT prior to manually removing an On-Line Resource. [ERCOT] Language Review — All
- 5. Operations Report Monthly Operations Report Summary/Questions — ERCOT
- 6. Operations Task Force Report Action Items: — Tammar
- 7. Texas RE Update Report Standards Updates — Penney
- 8. System Operations Report Operating Procedure changes that impact market participants. — ERCOT
- 9. Seminar Task Force Report OTS completed? — ERCOT/Allgower
-
10.
Other: ROS directive - Voltage support requirement for all Generation Resources greater than 20 MVA. (See Protocol Section 3.15, paragraph 2) Update on offline discussions. ERCOT Isabell is reviewing language submitted by Walter! Possible review of draft NPRR and NOGRR on Voltage Control Requirements. Update on EEA Workshop
— Walter/ERCOT Small Group Warren/ERCOT
- VAR-001-4 5 19 14_V20 · Stakeholder Presentation
- 11. Future Meeting Date: June 25th ERCOT Met Center room 168. — Owens
- Adjourn Voltage Control Workshop start at 1:00 pm — Owens · 12:00 pm
-
Voltage Control Workshop May 19th 2014 1:00pm 3:30pm ERCOT Met Center room 206B Review draft NPRR and NOGRR on Voltage Control requirements that the small group has been working on.
— Owens/Small Group
· 1:00 pm 3:30 pm
- VAR-001-4 5 19 14_V20 · Stakeholder Presentation