SMOGRR #22 · Revision Request

SMOGRR022  Related to NPRR948, Instrument Transformer Testing Schedule and Removal of Reference to Fiber-Optic Current Transformers

Approved sponsor ERCOT posted 2019-05-29 ercot.com
ReasonRemoves references to a technology no longer deployed or used for EPS Metering Facilities
Created2019-07-10
Approved2019-10-08
Sections Affected
7.27.5.37.5.3.4 (delete)and 7.5.3.6 (delete)
Summary
This Settlement Metering Operating Guide Revision Request (SMOGRR) removes references to fiber-optic instrument transformers.
Action Log 4 milestones
Documents 6
NameTypePostedClassification
022SMOGRR-01 Related to NPRR948, Instrument Transformer Testing Schedule, Removal of Reference to Fiber Optic CTs 052919 doc May 29 '19 Revision Request
022SMOGRR-02 Impact Analysis 052919 doc May 29 '19 Staff Report
022SMOGRR-03 WMS Report 071019 doc Jul 12 '19 Committee Report
022SMOGRR-04 WMS Report 080719 doc Aug 8 '19 Committee Report
022SMOGRR-05 TAC Report 092519 doc Sep 27 '19 Committee Report
022SMOGRR-06 Board Report 100819 doc Oct 11 '19 Committee Report
Meetings That Took It Up 5
DateMeetingCommitteeStatus
Oct 8 '19 Board of Directors Meeting BOARD Concluded
Sep 25 '19 TAC Meeting TAC Concluded
Aug 7 '19 WMS Meeting WMS Concluded
Jul 10 '19 WMS Meeting WMS Concluded
Jun 5 '19 WMS Meeting WMS Concluded