SMOGRR #15 · Revision Request
SMOGRR015 Administrative Changes for the June 1, 2014 Settlement Metering Operating Guide
ReasonAdministrative Change
Created2014-05-14
Sections Affected
10.5
Summary
This SMOGRR aligns the Settlement Metering Operating Guide (SMOG) with the Protocols as revised by Nodal Protocol Revision Request (NPRR) 584, Alignment with TAC Procedures to Shorten the Appeals Timeline, which was approved by the ERCOT Board on 4/8/14. This SMOGRR shortens the appeals timelines for appealing Metering Working Group (MWG) and WMS actions to align with the Electric Reliability Council of Texas Technical Advisory Committee Procedures and maintains accurate information as allowed by Section 10.1, Introduction.
Documents 1
| Name | Type | Posted | Classification |
|---|---|---|---|
| 015SMOGRR-01 Administrative Changes for the June 1, 2014 Settlem | doc | May 14 '14 | Revision Request |