SMOGRR #9 · Revision Request
SMOGRR009 Submittal Timeline for EPS Metering Design Proposals
- WMS Sep 22 '10
- TAC Oct 7 '10
- BOARD —
- PUCT —
ReasonThe submittal timeline in the SMOG in regards to EPS Metering Design Proposals will need to change to reduce risk associated with ERCOT generating production-ready network models.
Created2010-08-17
Sections Affected
3.2.1
Summary
This Settlement Metering Operating Guide Revision Request (SMOGRR) changes the timeline for Transmission and/or Distribution Service Provider (TDSP) submittal of ERCOT-Polled Settlement (EPS) Metering Design Proposal.
Timeline
- Jul 15
-
Aug 17
MWG MWG Meeting via WebEx: Review of Draft SMOGRRMWGRecommended for Approval“Consensus to recommend approval of SMOGRR009 as submitted.” — Passed→ MWG Impact Analysis review
-
Sep 21
MWG MWG Conference Call: Discussion and Impact Analysis on SMOGRR009MWGRecommended for Approval Forwarded → WMS“Consensus to endorse and forward the 8/17/10 MWG Report and Impact Analysis for SMOGRR009 to WMS.” — Passed→ WMS consideration of SMOGRR009
-
Sep 22
WMS WMS MeetingWMSRecommended for Approval“To recommend approval of SMOGRR009 as recommended by mwg in the 9/21/10 MWG Report.” — Passed→ TAC consideration of SMOGRR009
-
Oct 7
TAC TAC MeetingTACApproved“To approve SMOGRR009 as recommended by WMS in the 9/22/10 WMS Report.” — Passed
-
—
Posted since the last meeting