SCR #812 · Revision Request
SCR812 Create Intermittent Renewable Generation Integration Report
- PRS Oct 15 '20
- TAC Oct 28 '20
- BOARD Dec 8 '20
- PUCT —
ReasonOther: Improves market awareness regarding overall renewable generation at ERCOT
Created2020-09-10
Approved2020-12-08
Sections Affected
4.2.24.2.3
Summary
This System Change Request (SCR) creates the new Intermittent Renewable Generation Integration Report, similar to the current integration reports for wind power and solar power production.
Timeline
- Aug 13
-
Sep 10
PRS PRS MeetingPRSRecommended for Approval“to recommend approval of SCR812 as submitted” — Passed→ Impact Analysis Consideration
-
Oct 15
PRS PRS Meeting by Webex OnlyPRSRecommended for Approval Forwarded → TAC priority 2021 · rank 3250“to endorse and forward to TAC the 9/10/20 PRS Report and Impact Analysis for SCR812 with a recommended priority of 2021 and rank of 3250” — Passed→ Revision Request Consideration
-
Oct 28
TAC TAC Meeting by Webex OnlyTACRecommended for Approval“to recommend approval of SCR812 as recommended by PRS in the 10/15/20 PRS Report” — Passed→ Revision Request Consideration
-
Dec 8
BOARD Urgent Board of Directors Meeting – Teleconference Available by WebcastBOARDApproved“to approve SCR812 as recommended by TAC in the 10/28/20 TAC Report” — Passed
-
—
Posted since the last meeting