SCR #770 · Revision Request

SCR770  Revision to Outage Scheduler Entry for Resource Maintenance Outage Level Designation

Approved sponsor Luminant Energy Company LLC posted 2012-01-18 ercot.com
ReasonThe current Outage Scheduler system does not allow the user to provide all of the information ERCOT needs for optimal and precise Outage scheduling and actually could infer information in an incorrect way. The system needs to request additional information to adequately inform ERCOT of the need for a Maintenance Outage.
Created2012-02-23
Approved2012-05-15
Sections Affected
Not applicable
Summary
This System Change Request (SCR) will make a change to the Outage Scheduler system so that the Qualified Scheduling Entity (QSE) is able to schedule Level I, II and III Maintenance Outages in a way that coincides with the definition of these Maintenance Outages shown in Protocol Section 2.1. Currently the data entry into the Outage Scheduler allows the user to enter the start of the proposed Outage only and the system infers from that the Maintenance Level of the Outage. However, there are instances where the start of the Outage can actually be earlier than that required by the designated Maintenance Level. The system needs to be changed so that the user can enter the requested start date of the Outage separately from the duration of time allowed before the maintenance would prevent a Forced Outage.
Action Log 4 milestones
Documents 6
NameTypePostedClassification
770SCR-01 Revision to Outage Scheduler Entry for Resource Mainte doc Jan 18 '12 Revision Request
770SCR-02 PRS Report 022312 doc Feb 27 '12 Committee Report
770SCR-03 Impact Analysis 032112 doc Mar 21 '12 Staff Report
770SCR-04 PRS Report 032212 doc Mar 26 '12 Committee Report
770SCR-05 TAC Report 040512 doc Apr 5 '12 Committee Report
770SCR-06 Board Report 051512 doc May 15 '12 Committee Report
Meetings That Took It Up 7
DateMeetingCommitteeStatus
Mar 13 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Mar 12 '13 Qualified Scheduling Entity Managers Working Group (QMWG) Meeting QMWG Concluded
Feb 13 '13 Wholesale Market Subcommittee (WMS) Meeting WMS Concluded
Feb 12 '13 Qualified Scheduling Entity Managers Working Group (QMWG) Meeting QMWG Concluded
Apr 5 '12 Technical Advisory Committee (TAC) Meeting TAC Concluded
Mar 22 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded
Feb 23 '12 Protocol Revision Subcommittee (PRS) Meeting PRS Concluded