RRGRR #8 · Revision Request
RRGRR008 Alignment with NPRR705, Provides Consistency for References to the End Date of the Generation Interconnection Process
- ROS Oct 8 '15
- TAC Dec 16 '15
- BOARD —
- PUCT —
ReasonAdministrative
Created2015-07-14
Sections Affected
2
Summary
In the Resource Interconnection Handbook, the term “commercial operations” has a different meaning to Resource Entities and financial institutions involved in construction and financing of Generation Resources than it does in the context of performance testing by ERCOT for new Generation Resources. This Recourse Registration Glossary Revision Request (RRGRR) aligns the Resource Registration Glossary with NPRR705 by replacing various terms used to refer to the date on which Generation Resources complete the Resource interconnection process with the proposed defined terms “Commercial Operations Date” and “Resource Commissioning Date” to provide consistency for references to the end of the generation interconnection process.
Timeline
- May 20
- Jun 16
-
Jul 14
RDWG RDWG MeetingRDWGRecommended for Approval Amended by the RDWG comments“To recommend approval of RRGRR008 as revised by RDWG.” — Passed→ Impact Analysis Consideration
-
Aug 18
RDWG RDWG MeetingRDWGRecommended for Approval Forwarded → ROS“To endorse and forward to ROS the 7/14/15 RDWG Report and Impact Analysis for RRGRR008.” — Passed→ Revision Request Consideration
- Sep 3
-
Oct 8
ROSEmail Vote / Unlisted MeetingROSRecommended for Approval“To recommend approval of RRGRR008 as recommended by RDWG in the 8/18/15 RDWG Report.” — Passed→ Revision Request Consideration
- Oct 29
- Nov 19
-
Dec 16
TACEmail Vote / Unlisted MeetingTACApproved“To approve RRGRR008 as recommended by ROS in the 10/8/15 ROS Report.” — Passed
-
—
Posted since the last meeting