RMGRR105 Change to the IDR Meter Requirement Report Due to Inclusion of AMS Meters
- RMS Dec 14 '11
- TAC Jan 5 '12
- BOARD —
- PUCT —
ReasonAlignment with the Protocols to reflect the changes associated with implementation of Nodal Protocol Revision Request (NPRR) 251, Synchronization of PRR845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned.
Created2011-11-16
Sections Affected
7.13.2.1
Summary
This Retail Market Guide Revision Request (RMGRR) aligns the Interval Data Recorder (IDR) reporting requirements in the RMG with the Protocols due to the inclusion of Advanced Metering Systems (AMS) meters.
Timeline
- Oct 27
-
Nov 16
RMS RMS MeetingRMSRecommended for Approval“To to recommend approval of RMGRR105 as submitted.” — Passed→ RMS for Impact Analysis review.
-
Dec 14
RMS RMS MeetingRMSRecommended for Approval Forwarded → TAC“To endorse and forward the 11/16/11 RMS Report and the Impact Analysis for RMGRR105 to TAC.” — Passed→ TAC for consideration.
-
Jan 5
TAC Technical Advisory Committee (TAC) MeetingTACApproved“To approve RMGRR105 as recommended by RMS in the 12/14/11 RMS Report.” — Passed