RMGRR #100 · Revision Request
RMGRR100 Texas SET 4.0 including: Acquisition and Transfer of Customers from one REP to Another; Meter Tampering Transactional Solution
ReasonThis RMGRR provides the process for the large transition of ESI IDs as a result of an acquisition pursuant to P.U.C. Subst. R. 25.493, Acquisition and Transfer of Customers from one Retail Electric Provider to Another.
Created2011-07-20
Sections Affected
2.17.3.2.27.3.2.3.17.3.37.3.57.4.1.17.4.1.27.4.1.37.4.1.47.6.2.17.6.2.27.6.3.47.6.3.57.6.3.67.6.3.97.6.5.87.6.6.27.7.17.117.11.17.11.27.11.2.17.11.2.27.11.37.11.47.11.57.11.5.17.11.5.1.17.11.5.1.37.11.5.1.47.11.5.27.11.5.2.17.11.5.2.27.11.5.2.37.11.5.2.47.11.5.2.57.11.5.37.11.5.3.17.11.5.3.27.11.5.3.37.11.5.3.47.11.2 (new)7.11.2.1 (new)7.11.2.2 (new)7.11.2.3 (new)7.11.2.4 (new)7.11.2.4.1 (new)7.11.2.4.1.1 (new)7.11.2.4.1.2 (new)7.11.2.4.1.3 (new)7.11.2.4.1.4 (new)7.11.2.4.1.5 (new)7.11.2.4.2 (new)7.11.2.4.2.1 (new)7.11.2.4.2.2 (new)7.11.2.4.2.3 (new)7.11.2.4.3 (new)7.11.2.4.3.1 (new)7.11.2.4.3.2 (new)7.11.2.4.3.3 (new)7.11.2.4.3.4 (new)7.11.67.11.6.17.11.6.27.11.6.2.17.11.6.37.11.6.3.17.11.6.3.1.17.11.6.3.1.27.11.6.3.27.11.6.47.11.77.11.87.11.97.11.107.12.17.12.27.12.37.12.47.14.57.16.17.16.1.17.16.37.16.4.17.16.4.27.16.4.3.37.16.4.47.17.1.17.17.1.27.17.27.17.3.17.17.3.27.17.3.3.38.3.2.18.3.2.28.3.2.38.3.2.48.3.3.28.3.3.38.3.3.58.3.3.68.3.3.98.3.5.9.3.6.28.3.2.18.3.2.28.3.2.38.3.2.48.3.3.28.3.3.38.3.3.58.3.3.68.3.3.98.3.5.98.3.6.29Appendix D19Appendix D29Appendix F19Appendix F29Appendix F39Appendix F49Appendix F59Appendix F69Appendix F7
Summary
This Retail Market Guide Revision Request (RMGRR) defines the process for Mass Transition of Electric Service Identifiers (ESI IDs) from one Competitive Retailer (CR) to another CR when transitioning due to an acquisition as introduced with Nodal Protocol Revision Request (NPRR) 294,Texas SET 4.0 Including: Acquisition and Transfer of Customers From One REP to Another; Meter Tampering Transactional Solution.
Action Log 3 milestones
-
Jul 20
RMSRecommended for Approval→ RMS for Impact Analysis review.
-
Aug 17
RMSRecommended for Approval→ TAC for consideration.
-
Sep 1
TACApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Jul 20 '11 | RMS | To recommend approval of RMGRR100 as amended by the 7/18/11 Texas SET Working Group comments. | Passed |
| Aug 17 '11 | RMS | To voted to endorse and forward the 7/20/11 RMS Report as amended by the 8/3/11 CenterPoint Energy comments and the revised Impact Analysis for RMGRR100 to TAC. | Passed |
Documents 8
| Name | Type | Posted | Classification |
|---|---|---|---|
| 100RMGRR-01 Texas SET 4.0 including Acquisition and Transfer of | doc | Jun 30 '11 | Revision Request |
| 100RMGRR-02 Texas SET Working Group Comments 071811 | doc | Jul 18 '11 | Revision Request Comments |
| 100RMGRR-03 RMS Report 072011 | doc | Jul 25 '11 | Committee Report |
| 100RMGRR-04 CenterPoint Energy 080311 | doc | Aug 3 '11 | Revision Request Comments |
| 100RMGRR-05 Impact Analysis 080311 | doc | Aug 3 '11 | Staff Report |
| 100RMGRR-06 Revised Impact Analysis 081211 | doc | Aug 12 '11 | Staff Report |
| 100RMGRR-07 RMS Report 081711 | doc | Aug 18 '11 | Committee Report |
| 100RMGRR-08 TAC Report 090111 | doc | Sep 7 '11 | Committee Report |
Meetings That Took It Up 4
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Sep 1 '11 | TAC Meeting | TAC | Concluded |
| Aug 17 '11 | RMS Meeting | RMS | Concluded |
| Jul 20 '11 | RMS Meeting | RMS | Concluded |
| Jul 13 '11 | Joint MCT/TXSET Meeting | MCT | Concluded |