ReasonThis RMGRR provides guidelines for the installation and removal of an IDR Meter as it relates to the use of provisioned Advanced Meters.
Created2010-07-14
Sections Affected
7.4.1; 7.13; 7.13.1; 7.13.1.1; 7.13.1.2; 7.13.1.3; 7.13.2; 7.13.2.1 7.13.2.2; 7.13.2.3; 7.13.2.4; 7.14.1; 7.14.4; 7.14.5; 9Appendix H1; 9Appendix H2
Summary
This Retail Market Guide Revision Request (RMGRR) updates the process for optional removal of Interval Data Recorder (IDR) Meters under certain conditions for Premises where an Advanced Meter can be provisioned by the Transmission and/or Distribution Service Provider (TDSP). In addition, due to the proposed definition of an IDR Meter in Protocol Revision Request (PRR) 845, Definition for IDR Meters and Optional Removal of IDR Meters at a Premise Where an Advanced Meter Can be Provisioned, references to IDR and/or IDR Meter are being updated to ensure appropriate understanding and usage of the terms.
Timeline
-
Jun 17
RMSFiled by Terry Bates on behalf of the Retail Metering Working Group (RMGRR)
-
Jul 14
RMS RMS MeetingRMSRecommended for Approval Amended by the RMS comments“To recommend approval of RMGRR088 as revised by RMS.” — Passed→ RMS for Impact Analysis review.
-
Aug 11
RMS RMS MeetingRMSRecommended for Approval Forwarded → TAC“To endorse and forward the 7/14/10 RMS Report and revised Impact Analysis for RMGRR088 to TAC.” — Passed→ TAC for consideration.
-
Sep 2
TAC TAC MeetingTACApproved“To approve RMGRR088 as recommended by RMS in the 8/11/10 RMS Report.” — Passed
-
—