RMGRR071  Process Change for Review of Impact Analysis on Point to Point Transactions or Processes Between CRs and TDSPs That Have No Impact to ERCOT

Approved sponsor Rob Bevill and Kathy Scott on behalf of the Texas SET Working Group posted 2008-11-13 ercot.com
ReasonThis RMGRR allows for the Impact Analysis of RMGRRs that involve CRs and TDSPs only in their Point to Point transactions or processes to be reviewed and approved by RMS at the same meeting, allowing the RMGRR to proceed through the stakeholder process without being delayed until the next RMS meeting.
Created2008-12-10
Sections Affected
3.3.33.3.5
Summary
This Retail Market Guide Revision Request (RMGRR) allows for the Impact Analysis of RMGRRs that are limited to Point to Point transactions or processes between Competitive Retailers (CRs) and Transmission Distribution Service Providers (TDSPs) that have no impact to ERCOT to be reviewed and approved by the Retail Market Subcommittee (RMS) at the RMS meeting at which the RMGRR is first considered.
Action Log 3 milestones
Amendments
DateBodyMotionResult
Dec 10 '08RMS To recommend approval of RMGRR071 as amended by ERCOT comments and as revised by RMS.Passed
Documents 6
NameTypePostedClassification
071RMGRR-01 Process Change for Review of Impact Analysis on Poin doc Nov 13 '08 Revision Request
071RMGRR-02 ERCOT Comments 120208 doc Dec 3 '08 Revision Request Comments
071RMGRR-03 RMS Recommendation Report 121008 doc Dec 11 '08 Committee Report
071RMGRR-04 Impact Analysis 010709 doc Jan 7 '09 Staff Report
071RMGRR-05 RMS Recommendation Report 011409 doc Jan 14 '09 Committee Report
071RMGRR-06 TAC Action Report 020509 doc Feb 6 '09 Committee Report
Meetings That Took It Up 3
DateMeetingCommitteeStatus
Feb 5 '09 TAC Meeting TAC Concluded
Jan 14 '09 RMS Meeting RMS Concluded
Dec 10 '08 RMS Meeting RMS Concluded