RMGRR #31 · Revision Request

RMGRR031  IDR Installation Process

Approved sponsor Kathy Scott on behalf of the IDR Taskforce posted 2005-11-16 ercot.com
ReasonAt the April 2005 RMS meeting, an IDR Taskforce was created to develop a Market process to support the new Mandatory IDR Threshold of 700 kW (kVA) requirements effective October 1, 2005. One of the recommendations of the Taskforce is to create a new section outlining this process for inclusion in the Retail Market Guide.
Created2006-02-15
Sections Affected
7.13.2 Interval Data Recorder (IDR) Installation Process (New) Appendix (New)
Summary
This RMGRR was created to clearly identify the roles and responsibilities of each Market Participant in processing requests for Mandatory or Optional IDR Installation that complies with Protocol Section 18.6.1, Interval Data Recorder (IDR) Installation and Use in Settlement. This RMGRR also adds a new appendix for the IDR Installation Request Form.
Action Log 2 milestones
Documents 5
NameTypePostedClassification
031RMGRR-01 IDR Installation Process doc Nov 16 '05 Revision Request
031RMGRR-02 Impact Analysis doc Dec 20 '05 Staff Report
031RMGRR-03 IDR Taskforce Comments doc Jan 26 '06 Revision Request Comments
031RMGRR-04 RMS Recommendation Report doc Feb 20 '06 Committee Report
031RMGRR-05 TAC Action Report 030906 doc Mar 13 '06 Committee Report
Meetings That Took It Up 3
DateMeetingCommitteeStatus
Mar 9 '06 TAC Meeting TAC Concluded
Feb 15 '06 RMS Meeting RMS Concluded
Jan 11 '06 RMS Meeting RMS Concluded