RMGRR #31 · Revision Request
RMGRR031 IDR Installation Process
ReasonAt the April 2005 RMS meeting, an IDR Taskforce was created to develop a Market process to support the new Mandatory IDR Threshold of 700 kW (kVA) requirements effective October 1, 2005. One of the recommendations of the Taskforce is to create a new section outlining this process for inclusion in the Retail Market Guide.
Created2006-02-15
Sections Affected
7.13.2 Interval Data Recorder (IDR) Installation Process (New) Appendix (New)
Summary
This RMGRR was created to clearly identify the roles and responsibilities of each Market Participant in processing requests for Mandatory or Optional IDR Installation that complies with Protocol Section 18.6.1, Interval Data Recorder (IDR) Installation and Use in Settlement. This RMGRR also adds a new appendix for the IDR Installation Request Form.
Action Log 2 milestones
-
Feb 15
RMSApproved
-
Mar 9
TACApproved
Documents 5
| Name | Type | Posted | Classification |
|---|---|---|---|
| 031RMGRR-01 IDR Installation Process | doc | Nov 16 '05 | Revision Request |
| 031RMGRR-02 Impact Analysis | doc | Dec 20 '05 | Staff Report |
| 031RMGRR-03 IDR Taskforce Comments | doc | Jan 26 '06 | Revision Request Comments |
| 031RMGRR-04 RMS Recommendation Report | doc | Feb 20 '06 | Committee Report |
| 031RMGRR-05 TAC Action Report 030906 | doc | Mar 13 '06 | Committee Report |
Meetings That Took It Up 3
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Mar 9 '06 | TAC Meeting | TAC | Concluded |
| Feb 15 '06 | RMS Meeting | RMS | Concluded |
| Jan 11 '06 | RMS Meeting | RMS | Concluded |