ERCOT·WATCH Search ercot.com  ⌕
RMGRR #26 · Revision Request

RMGRR026  TDSP to TDSP Customer Transition Process

Approved sponsor Mass Transition TF posted 2005-07-11 ercot.com
ReasonThe purpose of this RMGRR is to provide the processes for handling a TDSP or Municipally Owned Utility or Electric Cooperative (MOU/EC) TDSP transition TDSP transition of ESI IDs. It covers the current process for a Partial Transition, high-level requirements for a transition when the ESI IDs change or remain the same, and the process for a Full Transition. This RMGRR is similar to the documentation developed for the mass transition of customers between CRs, recording the work of the ad hoc task force and includes a description of processes that could be used in future TDSP to TDSP transition events.
Created2005-08-10
Sections Affected
7.11
Summary
This RMGRR revises Sections 7.11.1 and 7.11.2 to include Transmission and/or Distribution Service Provider (TDSP) to TDSP customer transitions; renumbers and re-tittles Sections 7.11.3 through 7.11.8 to distinguish Competitive Retailer (CR) to CR transition language from TDSP to TDSP transition language; and adds new Sections 7.11.9 through 7.11.12 documenting the TDSP to TDSP transition processes.
Action Log 6 milestones
Documents 6
NameTypePostedClassification
026RMGRR-01 TDSP to TDSP Customer Transition Process 071205 doc Jul 12 '05 Revision Request
026RMGRR-02 RMS Recommendation Report 081005 doc Aug 16 '05 Committee Report
026RMGRR-03 Impact Analysis 090705 doc Oct 14 '05 Staff Report
026RMGRR-04 RMS Recommendation Report 091405 doc Sep 19 '05 Committee Report
026RMGRR-05 CBA 101305 xls Oct 13 '05 Committee Report
026RMGRR-06 TAC Recommendation Report 110305 doc Nov 7 '05 Committee Report
Meetings That Took It Up 2
DateMeetingCommitteeStatus
Nov 3 '05 TAC Meeting TAC Concluded
Oct 6 '05 TAC Meeting TAC Concluded