ERCOT·WATCH Search ercot.com  ⌕
RMGRR #10 · Revision Request

RMGRR010  Disconnect/Reconnect Process Guide Field Service Exceptions

Approved sponsor Cirro Energy, AEP posted 2004-06-14 ercot.com
Reason§§VII.D Field Service Exceptions has been added to convey the TDSP Field Service Representatives discretion that may be used when completing a disconnection order that may result in a hazardous condition at the premise. §§VII.F Force Majeure has been updated to indicate the TDSP notification process of force majeure events. §§VIII.B Other Charges has been updated to reflect Move Out activity on disconnected premises.
Created2004-06-14
Sections Affected
Disconnect Reconnect Process Guide §§VII.D; §§VII.F; and §§VIII.B
Summary
Disconnect Reconnect Process Guide; New Section Added: §§VII.D Field Service Exceptions, Section Updated: §§VII.F Force Majeure, Section Updated: §§VIII.B Other Charges.
Documents 1
NameTypePostedClassification
Field Service Exceptions doc Sep 30 '05 Revision Request