PGRR #139 · Revision Request
PGRR139 Related to NPRR1314, Planning Guide Glossary Transition
- ROS Feb 5 '26
- TAC Feb 25 '26
- BOARD Apr 21 '26
- PUCT May 29 '26
ReasonGeneral system and/or process improvement(s)
Created2026-01-08
Approved2026-05-29
Sections Affected
22.1 (delete)2.2 (delete)6.36.11
Summary
This Planning Guide Revision Request (PGRR) relocates each term and acronym from Section 2, Definitions and Acronyms, to Protocol Section 2, Definitions and Acronyms, and aligns related defined acronym usage. This PGRR also removes the seldom-used acronyms ‘Current Year (CY)’ and ‘Future Year (FY)’ in effort to avoid potential language confusion.
Timeline
- Dec 16
-
Jan 8
ROS ROS MeetingROSRecommended for Approval“to recommend approval of PGRR139 as submitted” — Passed→ Impact Analysis Consideration
-
Feb 5
ROS ROS MeetingROSRecommended for Approval Forwarded → TAC“to endorse and forward to TAC the 1/8/26 ROS Report and 12/16/25 Impact Analysis for PGRR139” — Passed→ Revision Request Consideration
-
Feb 25
TAC TAC MeetingTACRecommended for Approval“to recommend approval of PGRR139 as recommended by ROS in the 2/5/26 ROS Report” — Passed→ Revision Request Consideration
- Apr 20
-
Apr 21
BOARDEmail Vote / Unlisted MeetingBOARDRecommended for Approval“to recommend approval of PGRR139 recommended by TAC in the 2/25/26 TAC Report” — Passed→ Revision Request Consideration
-
May 29
PUCTPUCTApproved“to approve PGRR139 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization” — Passed
-
—
Posted since the last meeting