PGRR #132 · Revision Request
PGRR132 Update to Standard Generation Interconnection Agreement (SGIA) Requirement
- ROS Jan 8 '26
- TAC Jan 21 '26
- BOARD Feb 9 '26
- PUCT Mar 26 '26
ReasonGeneral system and/or process improvement(s)
Created2025-11-06
Approved2026-03-26
Sections Affected
5.2.8.1
Summary
This Planning Guide Revision Request (PGRR) clarifies new Resources must interconnect to the ERCOT System via a new SGIA.
Timeline
- Oct 1
-
Oct 2
Listed without action at 1 meeting
-
Nov 6
ROS ROS Meeting - Webex OnlyROSDeferred/Tabled Referred → PLWG“to table PGRR132 and refer the issue to PLWG” — Passed→ Language Consideration
-
Dec 4
ROS ROS Meeting - Webex OnlyROSRecommended for Approval Amended by the Nov 25 '25 ERCOT comments“to recommend approval of PGRR132 as amended by the 11/25/25 ERCOT comments” — Passed→ Impact Analysis Consideration
-
Jan 8
ROS ROS MeetingROSRecommended for Approval Forwarded → TAC“To endorse and forward to TAC the 12/4/25 ROS Report and 10/1/25 Impact Analysis for PGRR132” — Passed→ Revision Request Consideration
-
Jan 21
TAC TAC MeetingTACRecommended for Approval“To recommend approval of PGRR132 as recommended by ROS in the 1/8/26 ROS Report” — Passed→ Revision Request Consideration
-
Feb 9
BOARD Board of Directors MeetingBOARDRecommended for Approval“To recommend approval of PGRR132 as recommended by TAC in the 1/21/26 TAC Report” — Passed→ Revision Request Consideration
-
Mar 26
PUCTPUCTApproved“to approve PGRR132 and accompanying ERCOT Market Impact Statement as presented in Project No. 54445, Review of Protocols Adopted by the Independent Organization.” — Passed
-
—