PGRR #112 · Revision Request

PGRR112  Dynamic Data Model and Full Interconnection Study (FIS) Deadline for Quarterly Stability Assessment

Approved sponsor ERCOT posted 2023-09-20 ercot.com
ReasonGeneral system and/or process improvement(s)
Created2023-10-05
Approved2024-07-25
Sections Affected
5.3.2.5 and 5.3.5
Summary
This Planning Guide Revision Request (PGRR) establishes requirements for Interconnecting Entities (IEs) to submit dynamic data models and for Transmission Service Providers (TSPs) to submit final Full Interconnection Studies (FISs) for approval at least 45 Business Days prior to the quarterly stability assessment deadline. Projects will not be qualified for the quarterly stability assessment if dynamic data models and final FISs are submitted less than 45 Business Days prior to the deadline. This PGRR also establishes that an IE must notify ERCOT and lead TSP(s) of changes to FIS assumptions that occur after FIS completion and before Initial Synchronization. It further clarifies that ERCOT shall not include a Generation Resource or Settlement Only Generator (SOG) in a quarterly stability assessment if certain requirements are not met prior to the quarterly stability assessment deadline. ERCOT will be required to notify a Generation Resource or SOG if it is ineligible be included in a quarterly stability assessment for which it has timely submitted data.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Mar 7 '24ROS to recommend approval of PGRR112 as amended by the 1/17/24 ERCOT commentsPassed
Apr 4 '24ROS to endorse and forward to TAC the 3/7/24 ROS Report and the 4/1/24 Revised Impact Analysis for PGRR112 with a recommended effective date of December 1, 2024Passed
Ballots
DateBodyResultYesNoAbstain
Apr 15 '24 TAC Motion Passes 28 0 0 xls
Apr 4 '24 ROS 25 0 0 xls
Mar 7 '24 ROS Motion Carries 7.5 0 0 xls
Oct 5 '23 ROS Motion Carries 7.5 0 0 xls
Documents 15
NameTypePostedClassification
112PGRR-01 Dynamic Data Model and Full Interconnection Study (FIS) Deadline for Quarterly Stability Assessment 092023 docx Sep 20 '23 Revision Request
112PGRR-02 Impact Analysis 092023 docx Sep 20 '23 Staff Report
112PGRR-03 ROS Ballot 100523 xls Oct 10 '23 Revision Request Ballot
112PGRR-04 ROS Report 100523 docx Oct 10 '23 Committee Report
112PGRR-05 LCRA Comments 103123 docx Oct 31 '23 Revision Request Comments
112PGRR-06 ERCOT Comments 011724 docx Jan 17 '24 Revision Request Comments
112PGRR-07 ROS Ballot 030724 xls Mar 7 '24 Revision Request Ballot
112PGRR-08 ROS Report 030724 docx Mar 7 '24 Committee Report
112PGRR-09 Revised Impact Analysis 040124 docx Apr 1 '24 Staff Report
112PGRR-10 ROS Ballot 040424 xls Apr 6 '24 Revision Request Ballot
112PGRR-11 ROS Report 040424 docx Apr 6 '24 Committee Report
112PGRR-12 TAC Ballot 041524 xls Apr 17 '24 Revision Request Ballot
112PGRR-13 TAC Report 041524 docx Apr 17 '24 Committee Report
112PGRR-14 Board Report 061824 docx Jun 20 '24 Committee Report
112PGRR-15 PUCT Report 072524 docx Jul 29 '24 Committee Report
Meetings That Took It Up 17
DateMeetingCommitteeStatus
Oct 24 '24 RIWG Meeting - Webex Only RIWG Concluded
Aug 21 '24 RIWG Meeting - Webex Only RIWG Concluded
Jun 18 '24 Board of Directors Meeting BOARD Concluded
Apr 15 '24 TAC Meeting TAC Concluded
Apr 4 '24 ROS Meeting ROS Concluded
Mar 7 '24 ROS Meeting - Webex Only ROS Concluded
Feb 12 '24 PLWG Meeting PLWG Concluded
Feb 1 '24 ROS Meeting - Webex Only ROS Concluded
Jan 17 '24 PLWG Meeting PLWG Concluded
Jan 8 '24 ROS Meeting ROS Concluded
Dec 13 '23 PLWG Meeting - Webex Only PLWG Concluded
Dec 7 '23 ROS Meeting - Webex Only ROS Concluded
Nov 14 '23 PLWG Meeting PLWG Concluded
Nov 2 '23 ROS Meeting ROS Concluded
Oct 24 '23 DWG Meeting - Webex Only DWG Concluded
Oct 18 '23 PLWG Meeting PLWG Concluded
Oct 5 '23 ROS Meeting - Webex Only ROS Concluded