PGRR #109 · Revision Request

PGRR109  Dynamic Model Review Process Improvement for Inverter-Based Resource (IBR) Modification

Approved sponsor ERCOT posted 2023-07-18 ercot.com
ReasonStrategic Plan Objective 1
Created2023-08-03
Approved2024-04-11
Sections Affected
5.2.15.5and 6.2
Summary
This Planning Guide Revision Request (PGRR) introduces a new requirement for Interconnecting Entities (IEs) associated with Inverter-Based Resources (IBRs) to undergo a dynamic model review process prior to Resource Commissioning Date. Additionally, this PGRR mandates that Resource Entities owning or controlling operational IBRs must undergo a review process before implementing any changes to settings or equipment (e.g., protection and control settings) that could impact electrical performance and necessitate dynamic model updates. As part of the review process, ERCOT shall review the model quality tests submitted by an IE or Resource Entity. In the case of operational IBRs, the review process may require the interconnecting Transmission Service Provider (TSP) conducting a limited dynamic stability study to compare and evaluate the electrical performance before and after the proposed modifications.
Action Log 6 milestones
Amendments
DateBodyMotionResult
Dec 7 '23ROS to recommend approval of PGRR109 as amended by the 11/17/23 ERCOT commentsPassed
Ballots
DateBodyResultYesNoAbstain
Jan 24 '24 TAC Motion Passes 30 0 0 xls
Jan 8 '24 ROS Motion Carries 7.5 0 0 xls
Dec 7 '23 ROS Motion Carries 7.5 0 0 xls
Documents 17
NameTypePostedClassification
109PGRR-01 Dynamic Model Review Process Improvement for Inverter-Based Resource (IBR) Modification 071823 docx Jul 18 '23 Revision Request
109PGRR-02 Impact Analysis 071823 docx Jul 18 '23 Staff Report
109PGRR-03 ROS Ballot 080323 xls Aug 7 '23 Revision Request Ballot
109PGRR-04 ROS Report 080323 docx Aug 7 '23 Committee Report
109PGRR-05 TAEBA Comments 100423 docx Oct 4 '23 Revision Request Comments
109PGRR-06 ERCOT Comments 101023 docx Oct 10 '23 Revision Request Comments
109PGRR-07 Joint Commenters Comments 101723 docx Oct 17 '23 Revision Request Comments
109PGRR-08 ERCOT Comments 110723 docx Nov 7 '23 Revision Request Comments
109PGRR-09 ERCOT Comments 111723 docx Nov 17 '23 Revision Request Comments
109PGRR-10 ROS Ballot 120723 xls Dec 11 '23 Revision Request Ballot
109PGRR-11 ROS Report 120723 docx Dec 11 '23 Committee Report
109PGRR-12 ROS Ballot 010824 xls Jan 10 '24 Revision Request Ballot
109PGRR-13 ROS Report 010824 docx Jan 10 '24 Committee Report
109PGRR-14 TAC Ballot 012424 xls Jan 25 '24 Revision Request Ballot
109PGRR-15 TAC Report 012424 docx Jan 25 '24 Committee Report
109PGRR-16 Board Report 022724 docx Feb 28 '24 Committee Report
109PGRR-17 PUCT Report 041124 docx Apr 16 '24 Committee Report
Meetings That Took It Up 21
DateMeetingCommitteeStatus
Aug 8 '25 NOGRR245 Workshop III Concluded
Mar 10 '25 NOGRR245 Workshop II Concluded
Aug 21 '24 RIWG Meeting - Webex Only RIWG Concluded
Jun 12 '24 RIWG Meeting - Webex Only RIWG Concluded
Apr 16 '24 RIWG Meeting - Webex Only RIWG Concluded
Feb 27 '24 Board of Directors Meeting BOARD Concluded
Feb 22 '24 DWG Meeting - Webex Only DWG Concluded
Jan 24 '24 TAC Meeting TAC Concluded
Jan 8 '24 ROS Meeting ROS Concluded
Dec 12 '23 DWG Meeting - Webex Only DWG Concluded
Dec 7 '23 ROS Meeting - Webex Only ROS Concluded
Nov 14 '23 PLWG Meeting PLWG Concluded
Nov 2 '23 ROS Meeting ROS Concluded
Oct 24 '23 DWG Meeting - Webex Only DWG Concluded
Oct 18 '23 PLWG Meeting PLWG Concluded
Oct 5 '23 ROS Meeting - Webex Only ROS Concluded
Sep 19 '23 PLWG Meeting PLWG Concluded
Sep 7 '23 ROS Meeting ROS Concluded
Aug 15 '23 PLWG Meeting - Webex Only PLWG Concluded
Aug 11 '23 IBRWG Meeting - Webex Only IBRWG Concluded
Aug 3 '23 ROS Meeting ROS Concluded