PGRR #103 · Revision Request

PGRR103  Establish Time Limit for Generator Commissioning Following Approval to Synchronize

Approved sponsor ERCOT posted 2022-12-21 ercot.com
ReasonAddresses current operational issues
Created2023-01-05
Approved2023-10-12
Sections Affected
5.5
Summary
This Planning Guide Revision Request (PGRR) requires an Interconnecting Entity to complete all conditions for commercial operation of a Generation Resource or Energy Storage Resource (ESR) within 180 days of receiving approval for Initial Synchronization from ERCOT.
Action Log 7 milestones
Amendments
DateBodyMotionResult
Apr 6 '23ROS to recommend approval of PGRR103 as amended by the 3/23/23 PLWG commentsPassed
Jun 8 '23ROS to endorse and forward to TAC the 5/4/23 ROS Report and 6/6/23 Revised Impact Analysis for PGRR103 with a recommended priority of 2024 and rank of 4020Passed
Ballots
DateBodyResultYesNoAbstain
Jun 27 '23 TAC Motion Passes 30 0 0 xls
Jun 14 '23 PRS Motion Carries 7 0 0 xls
Jun 8 '23 ROS Motion Carries 7.5 0 1 xls
May 4 '23 ROS Motion Carries 7.5 0 0 xls
Apr 6 '23 ROS 2 0 0 xls
Apr 6 '23 ROS Motion Carries 7.5 0 1 xls
Jan 5 '23 ROS Motion Carries 7.5 0 0 xls
Documents 25
NameTypePostedClassification
103PGRR-01 Establish Time Limit for Generator Commissioning Following Approval to Synchronize 122122 docx Dec 21 '22 Revision Request
103PGRR-02 Impact Analysis 122122 docx Dec 21 '22 Staff Report
103PGRR-03 ROS Ballot 010523 xls Jan 9 '23 Revision Request Ballot
103PGRR-04 ROS Report 010523 docx Jan 9 '23 Committee Report
103PGRR-05 ERCOT Comments 013023 doc Jan 30 '23 Revision Request Comments
103PGRR-06 Joint Commenters Comments 021323 docx Feb 13 '23 Revision Request Comments
103PGRR-07 Southern Power Comments 022223 docx Feb 22 '23 Revision Request Comments
103PGRR-08 RWE Renewables Comments 022723 doc Feb 27 '23 Revision Request Comments
103PGRR-09 Joint Commenters Comments 022823 docx Feb 28 '23 Revision Request Comments
103PGRR-10 NextEra Energy Resources Comments 030123 doc Mar 1 '23 Revision Request Comments
103PGRR-11 Lubbock Power & Light Comments 030823 doc Mar 8 '23 Revision Request Comments
103PGRR-12 PLWG Comments 032323 docx Mar 23 '23 Revision Request Comments
103PGRR-13 ROS Ballot 040623 xls Apr 7 '23 Revision Request Ballot
103PGRR-14 ROS Report 040623 docx Apr 7 '23 Committee Report
103PGRR-15 ERCOT Comments 050323 doc May 3 '23 Revision Request Comments
103PGRR-16 ROS Ballot 050423 xls May 8 '23 Revision Request Ballot
103PGRR-17 ROS Report 050423 docx May 8 '23 Committee Report
103PGRR-18 Revised Impact Analysis 060623 docx Jun 6 '23 Staff Report
103PGRR-19 ROS Ballot 060823 xls Jun 9 '23 Revision Request Ballot
103PGRR-20 ROS Report 060823 docx Jun 9 '23 Committee Report
103PGRR-21 PRS Comments 061423 docx Jun 14 '23 Revision Request Comments
103PGRR-22 TAC Ballot 062723 xls Jun 29 '23 Revision Request Ballot
103PGRR-23 TAC Report 062723 docx Jun 29 '23 Committee Report
103PGRR-24 Board Report 083123 docx Sep 4 '23 Committee Report
103PGRR-25 PUCT Report 101223 docx Oct 16 '23 Committee Report
Meetings That Took It Up 18
DateMeetingCommitteeStatus
Dec 20 '23 RIWG Meeting - Webex Only RIWG Concluded
Oct 10 '23 RIWG Meeting - Webex Only RIWG Concluded
Aug 31 '23 Board of Directors Meeting BOARD Concluded
Jun 27 '23 TAC Meeting TAC Concluded
Jun 14 '23 PRS Meeting PRS Concluded
Jun 8 '23 ROS Meeting ROS Concluded
May 4 '23 ROS Meeting - Webex Only ROS Concluded
Apr 6 '23 ROS Meeting ROS Concluded
Mar 31 '23 OWG Meeting - Webex Only OWG Concluded
Mar 22 '23 PLWG Meeting PLWG Concluded
Mar 16 '23 OWG Meeting - Webex Only OWG Concluded
Mar 2 '23 ROS Meeting ROS Concluded
Feb 16 '23 OWG Meeting - Webex Only OWG Concluded
Feb 14 '23 PLWG Meeting PLWG Concluded
Feb 8 '23 ROS Meeting - Webex Only ROS Concluded
Jan 25 '23 PLWG Meeting PLWG Concluded
Jan 19 '23 OWG Meeting - Webex Only OWG Concluded
Jan 5 '23 ROS Meeting ROS Concluded