PGRR #70 · Revision Request

PGRR070  Revised Responsibilities for Performing Geomagnetic Disturbance (GMD) Vulnerability Assessments

Approved sponsor ERCOT posted 2019-02-19 ercot.com
ReasonRegulatory requirements
Created2019-03-07
Approved2019-06-11
Sections Affected
3.1.1.53.1.8and 6.11
Summary
This Planning Guide Revision Request (PGRR) aligns the Planning Guide with North American Electric Reliability Corporation (NERC) Reliability Standard TPL-007-2, Transmission System Planned Performance for Geomagnetic Disturbance Events, by identifying responsibilities for performing studies needed to complete benchmark and supplemental Geomagnetic Disturbance (GMD) vulnerability assessments.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Apr 4 '19ROS to recommend approval of PGRR070 as amended by the 3/25/19 ERCOT comments as revised by ROSPassed
May 2 '19ROS to endorse and forward to TAC the 4/4/19 ROS Report, as amended by the 4/25/19 ERCOT comments as revised by ROS, and the Impact Analysis for PGRR070 with a recommended priority of 2019 and a rank of 230Passed
May 22 '19TAC to recommend approval of PGRR070 as recommended by ROS in the 5/2/19 ROS Report as amended by the 5/17/19 ERCOT comments with a recommended effective date of upon system implementation for grey-boxed language and July 1, 2019 for all remaining language; and the Revised Impact AnalysisPassed
Documents 18
NameTypePostedClassification
070PGRR-01 Revised Responsibilities for Performing GMD Vulnerability Assessments 021919 docx Feb 19 '19 Revision Request
070PGRR-02 Impact Analysis 021919 doc Feb 19 '19 Staff Report
070PGRR-03 PGDTF Comments 030119 doc Mar 1 '19 Revision Request Comments
070PGRR-04 ROS Report 030719 docx Mar 8 '19 Committee Report
070PGRR-05 NRG Comments 031119 doc Mar 11 '19 Revision Request Comments
070PGRR-06 NRG Comments 031519 doc Mar 15 '19 Revision Request Comments
070PGRR-07 ERCOT Comments 032519 doc Mar 25 '19 Revision Request Comments
070PGRR-08 Oncor Comments 040219 doc Apr 2 '19 Revision Request Comments
070PGRR-09 CenterPoint Energy Comments 040319 doc Apr 3 '19 Revision Request Comments
070PGRR-10 ROS Report 040419 doc Apr 9 '19 Committee Report
070PGRR-11 ERCOT Comments 042519 doc Apr 25 '19 Revision Request Comments
070PGRR-12 NRG Comments 043019 doc Apr 30 '19 Revision Request Comments
070PGRR-13 ROS Report 050219 doc May 6 '19 Committee Report
070PGRR-14 PRS Comments 051019 doc May 10 '19 Revision Request Comments
070PGRR-15 Revised Impact Analysis 051419 doc May 14 '19 Staff Report
070PGRR-16 ERCOT Comments 051719 doc May 17 '19 Revision Request Comments
070PGRR-17 TAC Report 052219.DOC doc May 23 '19 Committee Report
070PGRR-18 Board Report 061119 doc Jun 11 '19 Committee Report
Meetings That Took It Up 10
DateMeetingCommitteeStatus
Jul 17 '19 PGDTF Meeting PGDTF Concluded
Jun 11 '19 Board of Directors Meeting BOARD Concluded
May 22 '19 TAC Meeting TAC Concluded
May 9 '19 PRS Meeting PRS Concluded
May 2 '19 ROS Meeting ROS Concluded
Apr 12 '19 PGDTF Meeting PGDTF Concluded
Apr 4 '19 ROS Meeting ROS Concluded
Mar 19 '19 PGDTF Meeting PGDTF Concluded
Mar 12 '19 PLWG Meeting PLWG Concluded
Mar 7 '19 ROS Meeting ROS Concluded