PGRR #60 · Revision Request
PGRR060 Clarification of Reliability Performance Criteria
ReasonAddresses current operational issues
Created2018-03-01
Approved2018-06-12
Sections Affected
4.1.1.2
Summary
This Planning Guide Revision Request (PGRR) updates the reliability performance criteria by defining unavailability of a Direct Current Tie (DC Tie) as a new contingency. The PGRR also includes clarification of the voltage level of transformers referred to in the reliability performance criteria.
Action Log 4 milestones
-
Mar 1
ROSRecommended for Approval→ Impact Analysis Consideration
-
Apr 5
ROSRecommended for Approval→ Revision Request Consideration
-
May 24
TACRecommended for Approval→ Revision Request Consideration
-
Jun 12
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Mar 1 '18 | ROS | To recommend approval of PGRR060 as revised by ROS. | Passed |
Documents 6
| Name | Type | Posted | Classification |
|---|---|---|---|
| 060PGRR-01 Clarification of Reliability Performance Criteria 021418 | doc | Feb 14 '18 | Revision Request |
| 060PGRR-02 Impact Analysis 021418 | doc | Feb 14 '18 | Staff Report |
| 060PGRR-03 ROS Report 030118 | doc | Mar 6 '18 | Committee Report |
| 060PGRR-04 ROS Report 040518 | doc | Apr 6 '18 | Committee Report |
| 060PGRR-05 TAC Report 052418 | doc | May 24 '18 | Committee Report |
| 060PGRR-06 Board Report 061218 | doc | Jun 14 '18 | Committee Report |
Meetings That Took It Up 7
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Jun 12 '18 | Board of Directors Meeting | BOARD | Concluded |
| May 24 '18 | TAC Meeting | TAC | Concluded |
| Apr 25 '18 | PLWG Meeting | PLWG | Concluded |
| Apr 5 '18 | ROS Meeting | ROS | Concluded |
| Mar 27 '18 | PLWG Meeting | PLWG | Concluded |
| Mar 1 '18 | ROS Meeting | ROS | Concluded |
| Feb 26 '18 | PLWG Meeting | PLWG | Concluded |