PGRR #58 · Revision Request
PGRR058 Clarification of Generation to be Included in the Planning Models
- ROS May 4 '17
- TAC May 25 '17
- BOARD Jun 13 '17
- PUCT —
ReasonAddresses current operational issues; Market efficiencies or enhancements
Created2017-03-22
Approved2017-06-13
Sections Affected
6.9
Summary
This Planning Guide Revision Request (PGRR) clarifies the specific generation intended to be included in the Planning Guide revisions of PGRR053, Addition of Proposed Generation Resources to the Planning Models, without the use of the term “All-Inclusive Generation Resource”. Section 5.1.1, Applicability, specifies the applicability requirements for proposed generation that must submit Generation Interconnection or Change Requests (GINRs) following the process described in Section 5, Generation Resource Interconnection or Change Request.
Timeline
- Mar 7
-
Mar 22
PLWG PLWG MeetingPLWGRecommended for Approval Amended by the PLWG comments“To recommend approval of PGRR058 as revised by PLWG.” — Passed→ Impact Analysis Consideration
-
Apr 19
PLWG PLWG WebEx MeetingPLWGRecommended for Approval Forwarded → ROS“To endorse and forward to ROS the 3/22/17 PLWG Report and Impact Analysis for PGRR058” — Passed→ Revision Request Consideration
-
May 4
ROS ROS MeetingROSRecommended for Approval“To recommend approval of PGRR058 as recommended by PLWG in the 4/19/17 PLWG Report” — Passed→ Revision Request Consideration
-
May 25
TAC TAC MeetingTACRecommended for Approval“To recommend approval of PGRR058 as recommended by ROS in the 5/4/17 ROS Report.” — Passed→ Revision Request Consideration
-
Jun 13
BOARD Board of Directors MeetingBOARDApproved“To approve PGRR058 as recommended by TAC in the 5/25/17 TAC Report.” — Passed