PGRR #45 · Revision Request
PGRR045 Alignment with NPRR705, Provides Consistency for References to the End Date of the Generation Interconnection Process
- ROS Nov 10 '15
- TAC Nov 19 '15
- BOARD Dec 8 '15
- PUCT —
ReasonAdministrative
Created2015-06-22
Approved2015-12-08
Sections Affected
5.3.25.4.35.4.55.4.105.7.15.7.2
Summary
In the Resource Interconnection Handbook, the term “commercial operations” has a different meaning to Resource Entities and financial institutions involved in construction and financing of Generation Resources than it does in the context of performance testing by ERCOT for new Generation Resources. This Planning Guide Revision Request (PGRR) aligns the Planning Guides with NPRR705 by replacing various terms used to refer to the date on which Generation Resources complete the Resource interconnection process with the proposed defined terms “Commercial Operations Date” and “Resource Commissioning Date” to provide consistency for references to the end of the generation interconnection process.
Timeline
- May 20
-
Jun 22
PLWGEmail Vote / Unlisted MeetingPLWGDeferred/Tabled“To table PGRR045.” — Passed→ Language Consideration
- Jul 22
-
Sep 15
PLWG PLWG MeetingPLWGRecommended for Approval“To recommend approval of PGRR045 as submitted.” — Passed→ Impact Analysis Consideration
-
Oct 19
PLWG PLWG WebEx MeetingPLWGRecommended for Approval Forwarded → ROS“To endorse and forward to ROS the 9/15/15 PLWG Report and Impact Analysis for PGRR045.” — Passed→ Revision Request Consideration
- Nov 5
-
Nov 10
ROSEmail Vote / Unlisted MeetingROSRecommended for Approval“To recommend approval of PGRR045 as recommended by PLWG in the 10/19/15 PLWG Report.” — Passed→ Revision Request Consideration
-
Nov 19
TAC TAC MeetingTACRecommended for Approval“To recommend approval of PGRR045 as recommended by ROS in the 11/10/15 ROS Report.” — Passed→ Revision Request Consideration
-
Dec 8
BOARD Board of Directors MeetingBOARDApproved“Approved PGRR045 as recommended by TAC in the 11/19/15 TAC Report.” — Passed