PGRR #39 · Revision Request
PGRR039 Generation Data for Resource Adequacy and Reliability Reporting
ReasonAddresses current operational issues and regulatory requirements.
Created2014-08-20
Approved2014-12-09
Sections Affected
5.3.25.5.1
Summary
This Planning Guide Revision Request (PGRR) proposes two changes to the Planning Guide. The first is new language in Section 5.3.2 that requires Interconnecting Entities (IEs) to provide certain information required for ERCOT’s Resource adequacy reports, Capacity, Demand and Reserves Report and the Seasonal Assessment of Resource Adequacy (SARA) Report, as well as for annual North American Electric Reliability Corporation (NERC) reliability assessment data requests. The second change, made to paragraph (2) of Section 5.5.1, ensures that ERCOT is a party to a decision by an IE and Transmission Service Provider (TSP) to execute a Standard Generation Interconnection Agreement (SGIA) before all interconnection studies have been completed and reviewed by the parties.
Action Log 6 milestones
-
Aug 20
PLWGRecommended for Approval→ PLWG for IA review.
-
Sep 17
PLWGRecommended for Approval→ ROS for consideration.
-
Oct 6
ROSDeferred/Tabled→ ROS for consideration
-
Oct 30
ROSRecommended for Approval→ TAC for consideration.
-
Nov 20
TACRecommended for Approval→ ERCOT Board for consideration.
-
Dec 9
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Aug 20 '14 | PLWG | To recommend approval of PGRR039 as amended by the 8/12/14 Sharyland comments and as revised by PLWG. | Passed |
Documents 9
| Name | Type | Posted | Classification |
|---|---|---|---|
| 039PGRR-01 Generation Data for Resource Adequacy and Reliability | doc | Jul 28 '14 | Revision Request |
| 039PGRR-02 Impact Analysis 072814 | doc | Jul 28 '14 | Staff Report |
| 039PGRR-03 Sharyland Comments 081214 | doc | Aug 12 '14 | Revision Request Comments |
| 039PGRR-04 PLWG Report 082014 | doc | Aug 21 '14 | Committee Report |
| 039PGRR-05 PLWG Report 091714 | doc | Sep 18 '14 | Committee Report |
| 039PGRR-06 ROS Report 100614 | doc | Oct 8 '14 | Committee Report |
| 039PGRR-07 ROS Report 103014 | doc | Nov 4 '14 | Committee Report |
| 039PGRR-08 TAC Report 112014 | doc | Nov 20 '14 | Committee Report |
| 039PGRR-09 Board Report 120914 | doc | Dec 10 '14 | Committee Report |
Meetings That Took It Up 7
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 9 '14 | Board of Directors Meeting | BOARD | Concluded |
| Nov 20 '14 | TAC Meeting | TAC | Concluded |
| Nov 18 '14 | PLWG Meeting | PLWG | Concluded |
| Oct 30 '14 | ROS Meeting | ROS | Concluded |
| Oct 22 '14 | PLWG Meetings | PLWG | Concluded |
| Oct 6 '14 | Joint ROS/WMS Meeting | ROS | Concluded |
| Aug 20 '14 | PLWG Meeting | PLWG | Concluded |