PGRR033  Dynamics Flat Start Cases Preparation

Approved sponsor Reza Ebrahimian on behalf of the Dynamics Working Group (DWG) posted 2013-09-23 ercot.com
ReasonThis PGRR aligns the Planning Guide with the ROS-approved Dynamics Working Group Procedural Manual, Revision 8, which requires ERCOT to prepare all flat start simulations after 1/1/15.
Created2013-10-23
Approved2014-02-11
Sections Affected
6.2.4
Summary
This Planning Guide Revision Request (PGRR) adds the requirement to the Planning Guide for ERCOT to prepare all flat start simulations. This PGRR also proposes non-substantive administrative changes to correct the title of the Dynamics Working Group Procedural Manual. These are shown below with the author "ERCOT Market Rules."
Action Log 6 milestones
Documents 8
NameTypePostedClassification
033PGRR-01 Dynamics Flat Start Cases Preparation 092313 doc Sep 23 '13 Revision Request
033PGRR-02 PLWG Report 102313 doc Oct 28 '13 Committee Report
033PGRR-03 Impact Analysis 112013 doc Nov 20 '13 Staff Report
033PGRR-04 PLWG Report 112213 doc Nov 26 '13 Committee Report
033PGRR-05 ROS Report 121213 doc Dec 16 '13 Committee Report
033PGRR-06 ROS Report 010914 doc Jan 13 '14 Committee Report
033PGRR-07 TAC Report 012814 doc Feb 12 '14 Committee Report
033PGRR-08 Board Report 021114 doc Feb 14 '14 Committee Report
Meetings That Took It Up 7
DateMeetingCommitteeStatus
Feb 11 '14 Board of Directors Meeting BOARD Concluded
Jan 28 '14 TAC Meeting TAC Concluded
Jan 22 '14 PLWG Meeting PLWG Concluded
Jan 9 '14 ROS Meeting ROS Concluded
Dec 12 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Nov 22 '13 Planning Working Group (PLWG) Meeting PLWG Concluded
Oct 23 '13 Planning Working Group (PLWG) Meeting PLWG Concluded