PGRR #23 · Revision Request

PGRR023  Contingency Filing Requirements

Approved sponsor PLWG posted 2012-10-10 ercot.com
ReasonThere are currently no requirements in the Protocols or Market Guides for TSPs to submit their contingency lists. The contingency definitions are critical for planning the ERCOT System.
Created2012-10-25
Approved2013-03-19
Sections Affected
6.9
Summary
This Planning Guide Revision Request (PGRR) adds a requirement for Transmission Service Providers (TSPs) to submit and annually review a list of contingencies for their portion of the ERCOT System. The language ensures that the appropriate contingencies are being submitted for ERCOT and North American Electric Reliability Corporation (NERC) planning criteria.
Action Log 5 milestones
Amendments
DateBodyMotionResult
Oct 25 '12PLWG Consensus to recommend approval of PGRR023 as revised by PLWG
Documents 7
NameTypePostedClassification
023PGRR-01 Contingency Filing Requirements 101012 doc Oct 10 '12 Revision Request
023PGRR-02 PLWG Report 102512 doc Oct 29 '12 Committee Report
023PGRR-03 Impact Analysis 103112 doc Oct 31 '12 Staff Report
023PGRR-04 PLWG Report 120412 doc Dec 7 '12 Committee Report
023PGRR-05 ROS Report 011013 doc Jan 14 '13 Committee Report
023PGRR-06 TAC Report 020713 doc Feb 8 '13 Committee Report
023PGRR-07 Board Report 031913 doc Mar 22 '13 Committee Report
Meetings That Took It Up 6
DateMeetingCommitteeStatus
Mar 27 '13 Planning Working Group (PLWG) Meeting PLWG Concluded
Mar 19 '13 Board of Directors Meeting BOARD Concluded
Feb 7 '13 Technical Advisory Committee (TAC) Meeting TAC Concluded
Jan 10 '13 Reliability and Operations Subcommittee (ROS) Meeting ROS Concluded
Dec 4 '12 Planning Working Group (PLWG) Meeting PLWG Concluded
Oct 25 '12 Planning Working Group (PLWG) Meeting PLWG Concluded