PGRR #21 · Revision Request
PGRR021 Synchronization with NPRR454, Removal of Unfunded Project List Language, and Modification of Administrative PGRR Definition
ReasonAlignment with the Protocols by removing language regarding the Unfunded Project List; including ERCOT’s opinion in TAC Reports; and allowing PGRRs that are for the purpose of alignment with Protocol Section 21 to proceed as Administrative PGRRs, significantly decreasing the amount of work and meeting time that must be devoted to these routine PGRRs.
Created2012-08-30
Approved2012-12-11
Sections Affected
1.2.11.2.4.51.2.4.81.2.4.101.2.4.111.2.4.12
Summary
This Planning Guide Revision Request (PGRR) aligns the Planning Guide with Nodal Protocol Revision Request (NPRR) 454 (approved by the ERCOT Board on July 17, 2012), which removed language regarding the Unfunded Project List; aligns the Planning Guide with the Protocols by requiring ERCOT’s opinion in the TAC Report; modifies the scope of the Administrative PGRR definition to include revisions for the purpose of maintaining consistency between Section 1.2.1 and Protocol Section 21, Revision Request Process; and includes administrative alignment changes.
Action Log 5 milestones
-
Aug 30
PLWGRecommended for Approval→ PLWG IA Review
-
Sep 25
PLWGRecommended for Approval→ ROS Consideration
-
Nov 8
ROSRecommended for Approval→ TAC Consideration
-
Nov 29
TACRecommended for Approval→ Board Consideration
-
Dec 11
BOARDApproved
Amendments
| Date | Body | Motion | Result |
|---|---|---|---|
| Nov 8 '12 | ROS | To recommend approval of PGRR021 as amended by the 10/2/12 ERCOT comments | Passed |
| Nov 29 '12 | TAC | To recommend approval of PGRR021 as amended by the 10/2/12 ERCOT comments. All Market Segments were present for the vote | Passed |
Documents 8
| Name | Type | Posted | Classification |
|---|---|---|---|
| 021PGRR-01 Synchronization with NPRR454, Removal of Unfunded Pro | doc | Aug 14 '12 | Revision Request |
| 021PGRR-02 Impact Analysis 081412 | doc | Aug 14 '12 | Staff Report |
| 021PGRR-03 PLWG Report 083012 | doc | Aug 31 '12 | Committee Report |
| 021PGRR-04 PLWG Report 092512 | doc | Sep 26 '12 | Committee Report |
| 021PGRR-05 ERCOT Comments 100212 | doc | Oct 2 '12 | Revision Request Comments |
| 021PGRR-06 ROS Report 110812 | doc | Nov 12 '12 | Committee Report |
| 021PGRR-07 TAC Report 112912 | doc | Nov 30 '12 | Committee Report |
| 021PGRR-08 Board Report 121112 | doc | Dec 12 '12 | Committee Report |
Meetings That Took It Up 5
| Date | Meeting | Committee | Status |
|---|---|---|---|
| Dec 11 '12 | Board of Directors Meeting | BOARD | Concluded |
| Nov 29 '12 | Technical Advisory Committee (TAC) Meeting | TAC | Concluded |
| Nov 8 '12 | Reliability and Operations Subcommittee (ROS) Meeting | ROS | Concluded |
| Sep 25 '12 | Planning Working Group (PLWG) Meeting | PLWG | Concluded |
| Aug 30 '12 | Planning Working Group (PLWG) Meeting | PLWG | Concluded |